7 Quick-start procedure
Before switching on the hydraulic unit :
• Check the electric wiring.
• Check the refrigeration circuit and make sure the gas
supply has been performed.
• Check the pressure of the hydraulic circuit (1-2 bar),
check that the heat pump is purged, and the rest of the
installation.
• Make sure that ALL DIP SW are OFF before starting
up. (figure
23 page 20
).
7 1 Start-up
-Turn ON the start/stop switch.
-Configure the hydraulic circuit (setting 5700) :
Presettings :
1. 1 heating circuit (by default).
2. 1 heating circuit and DHW tank.
3. 2 heating circuits.
4. 2 heating circuitsand DHW tank.
5. Boiler backup and 1 heating circuit.
6. Boiler backup and 2 heating circuits.
7. Boiler backup, 1 heating circuit
and DHW tank.
8. Boiler backup, 2 heating circuits
and DHW tank.
-Time, Date and time programs for HC1, HC2, DHW if
different than default values (settings 500 – 576).
-Ajust the heating curve slope (720; 1020) and curve
off-set (721; 1021).
The heat pump is ready for operation !
You can also :
1. Adjust the heating circuit setpoints if different
than default values (710 – 714; 1010-1014).
2. Adjust the DHW setpoints if different than
default values (1610-1612)
3. Start a legionella cycle (1640-1647).
4. Perform floor drying (850-857).
7 2 Start-up check-list
7 2 1 Defore starting-up
• Sight checks
Outdoor unite (see chapiter "Installation of the outdoor unit"
page 12
)
OK
Non compliant
Location and fittings, condensate evacuation.
Compliance with distances from obstacles.
• Hydraulic checks
Hydraulic unit (see chapiter "Installing the hydraulic unit"
page 15
)
OK
Non compliant
Value
Connection of pipes, valves and pumps (1 or 2 circuits, DHW).
Installation water volume (expansion vessel of adequate capacity ?).
No leaks.
Main system pressure and degassing (0,3bar > expansion vessel pre-loading).
• Refrigeration connections and checks
(see chapiters "Refrigeration connections"
page 16
and "filling the installation with gas"
page 19
)
OK
Non compliant
Connections between units (pipe length, flare tightening torque...).
Installation of HP, LP pressure switches on liquid line (small pipe).
Pump down required.
Nitrogen leak test (~ 25 bar).
Refrigerant filling of hydraulic unit and pipes.
Opening of refrigeration valves to outdoor unit.
Installation and operating manual "1364 - EN"
- 55 -
Heat pump split single service 3 phase