![Fujitsu AJ*108LALH Series Скачать руководство пользователя страница 36](http://html.mh-extra.com/html/fujitsu/aj-108lalh-series/aj-108lalh-series_installation-manual_118219036.webp)
En-36
PIPE INSTALLATION II
8.
A Connection system
Fig.
In case of connected 1 outdoor unit
A)
Outdoor unit
Pressure gauge
Vacuum
pump
Scale
Pressure regulating
valve
Nitrogen
Indoor
unit
Indoor
unit
In case of connected many outdoor units
B)
Pressure regulating valve
Pressure gauge
Outdoor unit
Outdoor unit
Nitrogen
Scale
Vacuum
pump
Indoor
unit
Indoor
unit
B
Fig.
Charging cap
Valve
Cap
Close
Hexagon
wrench
Close
Open
Open
Spindle
A
Table.
Pipe
Spindle
Cap
Charging cap
Liquid
valve
9.0 to 12.0 N·m
(90 to 120 kgf·cm)
20.0 to 24.0 N·m
(200 to 240 kgf·cm)
12.5 to 16.0 N·m
(125 to 160 kgf·cm)
Gas
valve
27.0 to 33.0 N·m
(270 to 330 kgf·cm)
25.0 to 30.0 N·m
(250 to 300 kgf·cm)
12.5 to 16.0 N·m
(125 to 160 kgf·cm)
Sealing test
8. 1.
CAUTION
Use only nitrogen gas.
•
Never use refrigerant gas, oxygen, in
fl
ammable gas or poisonous gas to pressurize the system. (If oxygen is
used. There is the danger of an explosion.)
Do not apply shock during sealing test.
•
It can rupture the pipes and cause serious injury.
Do not turn on the power unless all operations are complete.
•
Do not block the walls and the ceiling until the sealing test and the charging of the refrigerant gas have been
•
completed.
After connecting the pipes, perform an sealing test.
Recheck that the spindle of the 3-way valve are closed before performing a sealing test. (Fig. B)
Pour nitrogen gas through both the liquid pipe and the gas pipe.
Pressurize nitrogen gas to 4.2 MPa to perform the sealing test.
Check all
fl
are connection areas and brazed areas.
Then, check that the pressure has not decreased.
Compare the pressures after pressurizing and letting it stand for 24 hours, and check that the pressure has not de-
creased.
When the outdoor temperature changes 5 °C, the test pressure changes 0.05 MPa.
*
If the pressure has dropped, the pipe joints may be leaking.
If a leakage is found, immediately repair it and perform a sealing test again.
* Decrease the pressure of nitrogen gas before blazing
After completing the sealing test, release the nitrogen gas from both valves.
Release the nitrogen gas slowly.