U41169-J-Z156-4-74
71
Installation
Installing/Uninstalling the Subsystem in/from the Rack
11.4
Installing and Uninstalling the Storage
Subsystem in and from the Rack
V
●
Please observe the safety precautions and references to mounting
into the rack in
chapter “Important Notes” on page 13
●
At least two people are needed to position the server in the rack.
●
The rack can tip over if more than one unit is removed.
11.5
Requirements of the Rack
The rack systems of the Fujitsu Siemens Computers GmbH (19-Inch (Classic)
Rack, DataCenter Rack and PRIMECENTER Rack) fully support the installation
of the PRIMERGY server systems. The installation in rack systems of several
other manufacturers (3rd-Party Rack) available at present is supported to a
large part.
To accommodate the ventilation concept and ensure proper ventilation of the
components in the rack, any unused areas must be closed using dummy covers.
Power is supplied via the socket strips available in the rack.
The mounting of the cable management is described in detail in the Technical
Manual for the respective rack.