29
FORPARK AUSTRALIA | www.forparkaust.com.au
INSTALLATION MANUAL – FREE STANDING STATIC 23
November 2017
Spring Bridge continued..
To tighten the ropes, turn the turnbuckles uniformly (using a screwdriver or similar tool inserted into the hole
in the turnbuckle and rotating the turnbuckle clockwise), allowing for deflection of corner ropes of no more
that 100mm. When the ropes are taut, drill through the hole in the lower end of each of the turnbuckles,
right through the threaded bolts and out the other side, using a 9/64" (or 3.5mm) drill bit and insert a spring
pin. (This can be hammered out and replaced at a later date if the net needs adjusting.
Lay out the rubber belt
and fasten each end to the Spring Bridge Brackets
, sandwiching the rubber
between the underside of the bracket and plates supplied, using 20mm tri-lobe bolts and T-nuts (with the tri-
lobe entering from the top). Connect each rope through rubber to the support rails
using 40mm tri-lobes
entering from underneath, through a washer, the support rail, the rubber and into the eye-nut on the rope.
Apply loctite to the thread of the eye-nut and tighten.
STEPPERS
Fasten steppers to the uprights using 17mm tri-lobes. Dig holes for each upright. The Steppers can be
arranged in varying configurations but the distance between each should be approximately 500mm from
centre to centre. The heights to from finished ground level to the top of each stepper should be 200mm,
300mm, 400mm, 500mm, 400mm, 300mm and 200mm respectively. After placing the uprights in the holes
and ensuring that their depth is correct and that the uprights are vertical, concrete them into the ground. Fill
the top of the holes with soil, packing firmly.