2400VS SERIES

 

 

Erie Water Treatment Controls – Belgium

 

Page 6

 

Installation

 

 

Assembly

 

 

For proper assembly of control valve and resin tank, proceed as follows: 
 
1.

 

Rinse the resin tank well before use. 

2.

 

Attach the lower distributor to the riser tube using PVC-glue or a stainless steel pin. 

3.

 

Lower the riser tube into the resin tank so that it touches the bottom. 

4.

 

Cut  the  riser  tube  13  mm  (=  1/2”)  below  the  top  of  the  tank  threads  and  chamfer  the  tube  to  prepare  for 
insertion into the control valve. 

5.

 

Temporary plug the top of the riser tube to prevent resin from entering the tube and fill the tank with resin for 
max. 3/4 full. 

6.

 

Make  sure  the  O-ring  in  the  riser  insert  of  the  control  valve  is  in  the  correct  position;  screw  the  upper 
distributor onto the control valve. 

7.

 

Lubricate the threads, the top of the riser tube and the tank O-ring of the control valve. 

8.

 

Lower the control valve straight down onto the riser tube and screw it onto the tank. 

 
 

Installation 

 

!!! ATTENTION 
 

 

For  proper  functioning  of  the  unit,  incoming  water  pressure  should be  between  a  minimum of 1,4 bar during 
regeneration and a maximum of 8,3 bar in service; if  necessary, a pressure reducer must be installed ahead of 
the system. 

 

Installation must only be undertaken by a person competent in plumbing.  

 

All plumbing and electrical connections must be done in accordance with local codes. 

 

Do not install the unit too close to a water heater (min. 3 m of piping between outlet of unit and inlet of heater); 
water  heaters  can  sometimes  transmit  heat  back  down  the  cold  pipe  into  the  control  valve;  always  install  a 
check valve at the outlet of the system. 

 

If  the  control  valve  is  not  equipped  with  a  bypass,  a  three  valve  bypass  system  must  be  installed  to  enable 
bypassing during servicing.  

 
 
For proper installation of the unit, proceed as follows: 
 
1.

 

Inlet/outlet

:  connect  the  inlet  and  outlet  to  the  control  valve;  when  facing  the  front  of  the  control  valve,  the 

inlet is at the left and the outlet at the right side. 

2.

 

Drain line

: connect a hose to the drain line fitting on the control valve and secure it; insert the drain hose into 

a standpipe, with siphon if required; make sure the drain hose is: 

 

as short as possible, 

 

not elevated too much, 

 

free of kinks, 

 

as this will all create undesired counter-pressure.  

3.

 

Brine  line

:  an  aircheck  is  required  for  proper  brining  during  regeneration,  but  a  float-controlled  brine  valve 

system can be used as a double security; 3/8” polytube must be used to connect the brine system to the control 
valve; do not overtighten the nut.  

4.

 

Transformer

: make sure the power source carries the same rating as the transformer; plug transformers output 

lead (with plug ø 2,5 mm x 5,5 mm) into socket at the timers power lead and plug transformer into socket; the 
connection can be secured by means of the wire clip. 

 

Содержание 2400VS Series

Страница 1: ...A Division of Aquion Inc 2400VS SERIES Technical Manual...

Страница 2: ...age 10 Diagnostics level Page 13 Parts Replacement Printed Circuit Board Page 14 Drive motor Page 15 Injector Page 15 Backwash flow control Page 16 Brine refill flow control Page 16 Brine tee Page 16...

Страница 3: ...A Division of Aquion Inc Art Nr Tech_Man ENG 2400VS 2013 06...

Страница 4: ......

Страница 5: ...resin The throughput is dependent on the maximum permissible pressure drop for the complete water softener and the maximum permissible specific load of the resin generally taken as 40 litres soft wate...

Страница 6: ...g pressure Operating temperature Electrical rating 1 4 8 3 bar 20 120 psi 2 48 C 35 120 F 24V 50 Hz max 500 mA Regeneration Controller software regeneration initiation regeneration mode time of regene...

Страница 7: ...2400VS SERIES Erie Water Treatment Controls Belgium Page 3 Flow Diagrams SERVICE BACKWASH BRINE SLOW RINSE FAST RINSE BRINE REFILL...

Страница 8: ...1 2 23 2 27 1 70 3 94 3 45 0 68 1 06 2 01 1 63 2 42 2 46 1 97 4 28 4 14 0 68 1 17 2 04 1 78 2 61 2 65 2 20 4 58 The following table is only an indication and is valid for an inlet pressure of 3 bar an...

Страница 9: ...set by increments of 1 min The following tables are only an indication and are valid for a brine valve with a refill rate that equals or exceeds the rate of the refill flow control Brine refill F C Pr...

Страница 10: ...al connections must be done in accordance with local codes Do not install the unit too close to a water heater min 3 m of piping between outlet of unit and inlet of heater water heaters can sometimes...

Страница 11: ...press the scroll button again to switch the motor to full speed which will shorten the transfer time needed by the control valve to reach the next position 9 The motor will move the control valve into...

Страница 12: ...n the correct time of day during a period of several hours consequently in case of prolonged power failure the time of day might not be maintained if this happens the time of day indication will flash...

Страница 13: ...total remaining regeneration time the actual regeneration cycle and the remaining cycle time total remaining actual regen remaining regen time cycle cycle time The control valve can be reset to servic...

Страница 14: ...er access code i e key sequence needs to be entered In the programming modes a flashing indication implicates that this parameter can be adjusted by pressing the up button or down button in this techn...

Страница 15: ...Press the scroll button again the display will show Press the up button or down button to set the volume of resin 5 Press the scroll button again the display will show Press the up button or down butt...

Страница 16: ...ration is started 9 Press the scroll button again the display will show only when the regeneration mode was set to Delayed or Dlyd Immd Press the up button or down button to set the time of regenerati...

Страница 17: ...tions that have taken place since installation TotVol display shows the total water usage through the unit since installation LastRgn display shows the water usage at the moment of the last regenerati...

Страница 18: ...THE WATER PRESSURE Printed Circuit Board 1 Loosen the 3 front cover screws and remove the front cover 2 Disconnect all connectors from the PCB 3 Remove the flat cable of the 3 button control pad from...

Страница 19: ...cover together 3 Lift the valve cover away from the valve body 4 Remove the rotor assembly from the valve cover the white Teflon O ring will remain in the valve cover 5 Remove the seal plate from the...

Страница 20: ...f necessary 6 Install the rotor assembly into the valve body ensuring that the arrow on the worm gear is pointing directly towards the second tooth on the worm drive shaft facing the front of the cont...

Страница 21: ...ing inside of the float valves shaft 6 Install the float valve straight up into the float chamber of the valve body 7 Reverse the procedure for reassembly refer to Parts Replacement Gasket Timer head...

Страница 22: ...nting down mark on the drive shaft pointing up 1 if this is not the case refer to Parts Replacement Drive motor Step 2 Valve body 1 Remove the drain hose from the drain elbow 2 Remove the 6 bolts hold...

Страница 23: ...2400VS SERIES Erie Water Treatment Controls Belgium Page 19...

Страница 24: ...t 12 Leak at riser tube 12 Verify that riser tube is seated correctly and is not cracked Unit fails to regenerate Cause Solution 1 Faulty electrical supply 1 Verify electrical service fuse transfo 2 D...

Страница 25: ...refill flow control 3 Verify that flow control is free of debris Unit uses too much salt Cause Solution 1 Excessive water in brine tank 1 Refer to problem Excessive water in brine tank 2 Unit regener...

Страница 26: ...ributor 2 Verify that distributors are free of debris 3 Crushed lower and or upper distributor 3 Replace distributor s Drain flows continuously Cause Solution 1 Defective PCB 1 Replace PCB 2 Defective...

Страница 27: ...ecked annually 1 Clean out injector 2 Clean brine refill flow control 3 Clean backwash flow control 4 Verify correct functioning of flow meter clean impeller if necessary 5 Verify programming of timer...

Страница 28: ...2400VS SERIES Erie Water Treatment Controls Belgium Page 24 Exploded Views Part Numbers Electronic timer...

Страница 29: ...ief flow meter cable 7 15 222 Screw back plate 2x 8 71502 Screw timer cover 3x 9 70962 Back plate 10 2100 206 Drive shaft 11 15 222 Screw drive motor assy 2x 12 72261 Drive motor 13 568 227 2 Worm 14...

Страница 30: ...2400VS SERIES Erie Water Treatment Controls Belgium Page 26 Valve body...

Страница 31: ...7 L Sleeve mixing valve 25 568 385 2 Brine refill flow control 26 186 118 O ring refill elbow 27 568 336 Refill elbow 28 541 275 Check ball refill elbow 29 413 62 Spring refill elbow 30 21 88 Nut refi...

Страница 32: ...30 24VAC 12VA UK plug J no transfo I Injector 4 1 2 5 B Backwash flow control 0 no flow control Nr Gal min L min E 1 6 6 1 F 1 8 6 8 G 2 0 7 6 H 2 2 8 3 J 2 6 9 8 T 3 0 11 4 K 3 5 13 2 L 4 0 15 1 M 5...

Страница 33: ......

Отзывы: