6.2
Commissioning the synchronized systems
1.
Wire the drives according to instructions.
2.
Connect the control boxes using the PXD SYNC-2 cable for two control boxes, or the PXD SYNC-4
cable for 2, 3 or 4 control boxes.
3.
Only one manual control switch is necessary. The control box with the manual control switch is the
master control box
. All other control boxes are subordinated.
4.
Connect the control boxes to the mains.
(Clicking sound of the control box
→
ready for initial operation)
5.
Carry out the initial operation according to chapter 4.
ATTENTION
The SYNC cable must be connected to the control box before the control box is connected to
the mains. If the SYNC cables are connected afterwards, they will not be recognised by the
control box and only one drive will move, which can lead to jamming of the entire system.
NOTE
When disconnecting the SYNC cable uncarefully, the plug can be ripped out of the print
platine!
6.3
Operation scenarios - FAQ
Scenario: connecting the manual control switch to another control box
→
Display blinks «- - -«
→
Manual control switch doesn’t work
→
Manual control switch ONLY works on the the master control box
Scenario: disconnecting or reconnecting the synchronisation cable
→
Display blinks «000»
→
Then display blinks «E93»
→
Perform a Reset «S 0» according to chapter 5.6.2 (all controls are reset to factory settings)
Scenario: power cut
→
Control box saves all stored positions
→
Synchronisation is stored
→
Getting back the power, the system can be used as usual. No initial operation necessary.
Scenario: power cut on only one control box
→
Display blinks «000»
→
Then display blinks «E93»
→
Perform a Reset «S 0» according to chapter 5.6.2 (all controls are reset to factory settings)