14
EN
5.3 Installation site and requirements
The steam generator is designed for installation outside steam room (sauna) only and should be
connected to the steam room (sauna) with a steam pipeline. The following ambient climate condi-
tions should be observed at the installation site:
•
Ambient temperature during operation 5°C to 40°C
•
Air humidity during operation 30% to 75% rel. air humidity
•
Storage temperature 0°C to 60°C
5.4 Mechanical installation
The SteamRock Basic is a wall-hanging device. It is mounted to the wall with 4 screws. Please en-
sure that the wall is able to carry the load of min. 45 kg. We recommend to allow certain reserve
for safety. Please consider that the steam generator is subject to light vibrations during operation.
To mount the steam generator first take the outer housing off the chassis. See pic. 1 below.
•
Remove two fixation screws at the bottom side on the left and on the right.
•
Pull the side walls of the housing slightly apart, so that the mounting flaps of the housing
are not blocked by the chassis.
•
Tilt the housing with the bottom slightly forward (from wall) and lift it upwards. Take the
housing off the chassis.
1.
3.
4.
2.
knock-out circle for steam
pipe installation upwards
Pic. 1
alle Maße in mm
535
670
min. 250
1000
460
420
min. 100
min. 100
all sizes in mm