17
6.5 Preparation
• Installation tools: crimping pliers for binding post and RJ11, 6 driller, screwdriver and manual wrench.
Figure 13:
installation tools
!
WarNINg!
Before installation and maintenance, check that both the AC and DC sides do
not carry electricity. If the DC side has just been disconnected, capacitors will
still contain electricity; therefore, please wait for at least 5 minutes to ensure the
capacitors completely release the energy and the inverter is not electrified.
NOTE:
Inverters should be installed by a technician.
6.6 Installation steps
Step 1
Drill 5 holes in the wall with 6 drill piece according to the size of bracket. Keep drilling vertical to the wall,
and don’t shake when drilling to avoid damage to the wall. The depth of the holes should be about 30mm.
After removing the dust in the holes, measure the net depth of the holes. If the depth is deeper than 33mm
or less than 27mm, the expansion tubes should not be installed and tightened.
Figure 14:
installation of the expansion pipe
expansion screw
expansion pipe
Содержание 1000TL
Страница 39: ...Notes ...