6 Commissioning
Levelflex M FMP 40 with Foundation Fieldbus
56
EHauser
6
Commissioning
6.1
Function check
Make sure that all final checks have been completed before you start up your measuring
point:
•
Checklist “Post installation check” (see page 28 ff.).
•
Checklist “Post connection check” (see page 31 ff.).
6.2
Switching on the measuring device
When the instrument is switched on for the first time, the following messages appear on
the display:
⇒
⇓
After 5 s, the following message appears
⇓
After 5 s or after you have pressed
F
the
following message appears
Select the language
(this message appears the first time the
instrument is switched on)
⇓
Select the basic unit
(this message appears the first time the
instrument is switched on)
⇓
The current measured value is displayed
⇓
After
F
is pressed, you reach the group
selection.
This selection enables you to perform the basic
setup