Float Tank Gauge LT11/12
14
Hauser
3.5.2
Guide Pipe connection
• Make sure to remove all the welding or cut off particles inside of the pipe.
• Use activated sealing, in order to maintain the airtight state in the locations such as flange connection points.
3.6
Top anchor, hook & base plate set up location
LT12 (flange connection)
*In case of LT11,
process connection uses a socket instead of a flange.
Unusable pipe
Usable pipe
Vertical
Remove
welding
burr
Welding
burr
Welding
Bending
by welding
Vertical
Chamfering
Burr
Tank top
Nozzle flange for Top anchor
Nozzle flange for Gauge head
3 Installation