Float Tank Gauge LT11/12
Hauser
11
3
Installation
3.1
Incoming acceptance, transport, storage
3.1.1
Incoming acceptance
Check the packing and contents for any signs damage.
Check the shipment, make sure nothing is missing and that the scope of supply matches your order.
3.1.2
Transport
Follow the safety instructions and transport conditions for instruments of more than 18 kg.
3.1.3
Storage
Pack the measuring instrument so that it is protected against impacts for storage and transport.
The original packing material provides the optimum protection for this.
The permissible storage temperature is -20...+70 °C.
3.2
Installation location
Note!
The LT 11/12 gauge head should be installed in a place where it is easy to read the scale.
Caution!
Tank enough space between the liquid inlet, agitator, and the float. Make sure the fluid entering the tank will
not hit the float directly.
If it is inevitable to install a float where it is facing the liquid inlet, setup a shield in front of the float so that the
wave will not directly hit the float.
Center of the float
Wave guard
Tank
liquid inlet
Wave guard
liquid inlet
[Recommended installation]
[Not recommended installation]
liquid inlet
liquid inlet
3 Installation