Recommissioning
Recommissioning is required when the measurement station is to be made operational
after a short time offline (<= 4 weeks). Follow these instructions if the system is to
operate safely and reliably:
•
Make sure that all water connections and internal screw connections are tight
•
Run a visual control of the electronic compartment making sure that there are no loose
connections
•
Check the sensors and if required, recalibrate. Take note of the respective sensor
operating instructions! (Section 5 in the ring binder)
•
Define and activate the water sampler programme
6.3
Device set-up
In order to set up the water sampler programme, read chapters 6.3 to 6.6 in the ’ASP-
Station 2000’ operating instructions (