System Startup
User Manual
October 2015
QCL-MAN-CT2211-Aerosol-Leak-Detection-System-Rev F
System Startup
12
3
System Startup
The aerosol leak detection system must be installed and fully commissioned prior to
customer operation.
Ensure that all cables are correctly terminated and the components on the production
line are correctly mounted. The control console must also be securely mounted with
clear access around. The shutdown signal from the line PLC must be set to not switch
the system off otherwise the system will begin to shutdown straight after booting.
The system is activated by turning the isolation switch (shown below) to the ON
position. The system must have been off for at least 30 seconds in order to boot
correctly.
Figure 3-1 Isolation switch
Isolation switch