shows the inner rail without the server attached.
Figure 24 Aligning the inner rail with white plastic guide block
CL5093
3. Slide the server into the cabinet so the inner rails extends over the plastic guide
blocks and the first part of the ball bearing retainer assemblies (
shows the inner rail without the server attached.
Figure 25 Inner rail over the first part of ball bearing retainer assembly
CL5094
4. Once the inner rails are properly engaged with the ball bearing retainer assemblies,
push the server into the cabinet until the slide rails are engaged and locked.
An audible click indicates that the slide rails are engaged and locked.
5. On the outside of each rail assembly, slide the blue disconnect tab forward to unlock
the server, and push the server completely into the cabinet (
Installing the server on the rails in the cabinet
25