UPS Adira (6kVA, 6kVA XL, 10kVA,
10kVA XL 1-phase)
UPS Installation and Connection
Adira series
45
6.5
Operating procedure for the connection with an
external battery
The nominal DC voltage of the external battery pack is 240VDC. Each battery
pack consists of 20 pieces of 12V maintenance-free batteries in series. To
achieve a longer back-up time, several battery packs can be connected, but the
principle of "same voltage, same type" has to be strictly observed.
The procedure for the installation of the battery bank must be strictly observed,
to avoid the risk of an electric shock.
Use only the items listed under accessories. This includes the compatible
battery bank and the corresponding connecting cable.
Ensure that the output voltage of the battery bank is identical with the DC-
input voltage of the UPS. Should this not be the case, the units may not be
connected with each other under any circumstances.
You must make sure that the UPS is switched off and that the circuit
breaker of the battery bank is removed before connecting the UPS with the
battery bank.
Connect the external battery pack with the UPS.
Install the circuit breakers of the battery bank.
Switch the input breaker of the UPS to "ON". Now the UPS begins to
charge the battery bank.
Содержание ABADX120009XX600
Страница 83: ...UPS Adira 6kVA 6kVA XL 10kVA 10kVA XL 1 phase Conformity Declarations Adira series 83 Adira 6kVA XL...
Страница 84: ...UPS Adira 6kVA 6kVA XL 10kVA 10kVA XL 1 phase Scope of Delivery Optional Accessories Adira 10kVA...
Страница 85: ...UPS Adira 6kVA 6kVA XL 10kVA 10kVA XL 1 phase Conformity Declarations Adira series 85 Adira 10kVA XL...
Страница 86: ...UPS Adira 6kVA 6kVA XL 10kVA 10kVA XL 1 phase Notes...
Страница 87: ...UPS Adira 6kVA 6kVA XL 10kVA 10kVA XL 1 phase Notes Adira series 87...