Eaton 9355 UPS (20/30kVA) Installation and Operation Manual 164201626—Rev F
www.eaton.com/powerquality
21
Chapter 5
Electrical Installation
The Eaton 9355 has the following power connections:
l
3-phase (L1, L2, and L3), neutral, and ground connection for rectifier/bypass input
l
3-phase (L1, L2, and L3), neutral, and ground connection for load output
The nominal input/output voltages are:
l
120/208 or 127/220 Vac (UPS only or parallel system)
l
208V, 480V, or 600V 60-Hz input is available when using the Options Cabinet with an input isolation
transformer
l
480/480 Vac is available when using the Options Cabinet with an output transformer
Output overcurrent protection and disconnect switch must be provided by others.
Figure 24 through Figure 31 beginning on page 37 show the oneline diagrams.
WARNING
Only qualified service personnel (such as a licensed electrician) should perform the UPS installation.
Initial startup must be performed by an authorized Eaton Customer Service Engineer. Risk of electrical
shock.
Wiring Preparation
To begin wiring the UPS or Options Cabinet:
1.
Verify that the electrical connections to the installation site have been properly installed.
2.
A wall-mounted, user-supplied, readily-accessible disconnection device must be incorporated in the input
wiring.
Compare the circuit breaker ratings to the ones in Table 1 on page 35.
Note:
To accommodate the feature of easy system expandability, it is recommended that initial installation
of the Eaton 9355 UPS contain wiring to support the maximum capacity of the UPS cabinet.
3.
Switch off utility power to the distribution point where the UPS or Options Cabinet will be connected. Be
absolutely sure there is no power.
4.
Determine your equipment's grounding requirements according to your local electrical code.
5.
Remove the UPS front door (see page 10).
6.
Verify that the UPS input circuit breaker is in the OFF position (see Figure 12).
7.
Verify that the UPS battery circuit breaker is in the OFF position.
8.
If you ordered the UPS with the optional output circuit breaker, verify that the output circuit breaker is in
the OFF position.
9.
Remove the UPS wiring access cover and retain.
10. Remove the UPS connections insulator and retain
Содержание Powerware 9355
Страница 1: ...Eaton 9355 UPS 20 30 kVA Installation and Operation Manual...
Страница 2: ......
Страница 3: ...Eaton 9355 UPS 20 30 kVA Installation and Operation Manual...
Страница 99: ......
Страница 100: ...164201626 D 164201626 F...