Vacuum fault interrupter (VFI)

Eaton’s Cooper Power series VFI transformers utilize 

vacuum interrupters to provide fault current interruption and 

load make/break switching capabilities. The VFI transformer 

uses the same technology used in Eaton’s Cooper Power 

series VFI pad-mounted switchgear.
VFI transformers can be specified for either transformer 

protection or loop protection. A VFI transformer with 

transformer protection protects the transformer and 

provides proper coordination with upstream protective 

devices. A VFI transformer with loop protection protects 

the loop or downstream section of a feeder. Consequently, 

when a fault occurs downstream, the VFI breaker trips and 

isolates the fault, leaving the transformer load uninterrupted.
The VFI interrupter mechanism in a VFI transformer has a 

hotstick-operable handle located on the faceplate of the 

transformer, with the operating mechanisms configured 

for ganged three-phase operation (see Figure 24). The VFI 

interrupter mechanism is opened by pulling the operation 

handle down to the open position. The VFI interrupter 

mechanism is closed by briskly pushing the handle up, 

into the closed position. If the VFI interrupter mechanism 

has tripped as the result of a fault or overload condition, 

the mechanism must be reset before it can be closed. To 

reset the mechanism, firmly pull the operation handle down 

toward the ground until the latch resets. After the latch has 

been successfully re-set, the VFI interrupter mechanism can 

be closed normally.

Figure 24.  VFI operating handle.

IMPORTANT

For 75 °C AWR transformers, applications with 

maximum ambient temperatures exceeding 30 °C or 

loading in excess of nameplate rating, contact your 

Eaton representative.

WARNING

Hazardous voltage. Can cause severe injury, death, or 

damage to equipment.

•  Do not operate loadbreak equipment if a fault 

condition is suspected. Doing so can cause an 

explosion or fire.

•  Use a hotstick to operate transformer loadbreak 

equipment. 

•  After operating transformer loadbreak equipment, 

check that voltages at transformer terminals are 

the expected values. Checking voltages verifies that 

loadbreak equipment operated properly and that 

electrical circuit conditions are as expected.

•  Before servicing transformer secondary connected 

equipment, verify that all transformer secondary 

terminals have zero voltage and ground the 

transformer secondary terminals following industry 

accepted safe grounding practices. Grounding 

secondary terminals protects against situations such 

as a standby generator energizing transformer from 

the secondary circuit.

•  Before servicing transformer, ALWAYS de-energize 

the transformer from a remote upstream source and 

then proceed to ground all primary and secondary 

transformer terminals following industry accepted 

safe grounding practices. Grounding secondary 

terminals protects against situations such as a 

standby generator energizing transformer from the 

secondary circuit.

•  Follow industry accepted safety practices. Utilize 

protective clothing and equipment when working 

with loadbreak equipment.

WARNING

Three-phase pad-mounted transformers use 

conventional transformer oil, R-Temp fluid, or 

Envirotemp™ FR3™ fluid for an insulating liquid. When 

the insulating liquid temperature is less than -20 °C 

(-4 °F) for conventional transformer oil, less than 0 °C 

(32 °F) for R-Temp fluid or less than -10 °C (14 °F) for 

Envirotemp™ FR3™ fluid, viscosity is reduced, which 

may reduce make and break capabilities of loadbreak 

devices. Below these temperatures, under-oil loadbreak 

accessories should not be used to make or break a 

load. Instead, de-energize transformer from a remote 

upstream source before operating under-oil loadbreak 

devices.

15

Three-phase pad-mounted compartmental type installation and maintenance instructions

   

MN202001EN   August 2015

Содержание COOPER POWER SERIES

Страница 1: ...ER POWER SERIES Distribution Transformers MN202001EN Effective August 2015 Supersedes S210 12 1 August 2013 Three phase pad mounted compartmental type transformer installation and maintenance instruct...

Страница 2: ...NTRACT BETWEEN THE PARTIES ANY SUCH CONTRACT STATES THE ENTIRE OBLIGATION OF EATON THE CONTENTS OF THIS DOCUMENT SHALL NOT BECOME PART OF OR MODIFY ANY CONTRACT BETWEEN THE PARTIES In no event will Ea...

Страница 3: ...Loadbreak Switches 11 Tap Changer 12 Dual Voltage and Delta Wye Switch 14 Vacuum Fault Interrupter VFI 15 Air Switches Arc Strangler 16 Surge Arresters 17 MAINTENANCE Exterior Maintenance 19 Cabinet I...

Страница 4: ...ions when working around high voltage lines and equipment and support our Safety For Life mission Safety information DANGER Hazardous voltage Contact with hazardous voltage will cause death or severe...

Страница 5: ...er capacity When using a forklift lift with the transformer tank closest to the mast of the forklift since most of the transformer weight is in the tank Pallet mounted equipment may also be moved by c...

Страница 6: ...abinet the installation will not provide the security needed to prevent tampering by the public Add a permanent mortar seal to fill the gaps Pre service inspection exterior New transformers or transfo...

Страница 7: ...e on underside of the tank cover or man hole cover 2 Loose shifted or damaged parts bushings fuse holders etc 3 Broken or loose connections 4 Contaminated insulating liquid sediment or foreign objects...

Страница 8: ...ransformer nameplate Transformer neutrals must be connected to system neutrals Leads and connections that are not used must be insulated from ground and all other leads Livefront transformer connectio...

Страница 9: ...furnished with the transformer Liquid temperature gauge Transformers may be furnished with a temperature gauge as optional equipment to indicate the top liquid temperature in the tank in degrees Cels...

Страница 10: ...sformer Pressure relief device Transformers may have a cover mounted pressure relief device PRD in addition to the faceplate mounted pressure relief valve PRV standard on all three phase pad mounted d...

Страница 11: ...minals following industry accepted safe grounding practices Grounding secondary terminals protects against situations such as a standby generator energizing transformer from the secondary circuit Foll...

Страница 12: ...valve to open valve Hold the valve open for 30 seconds after pressurized air can no longer be heard hissing through the valve 2 Close pressure relief valve and wait 30 seconds 3 Pull pressure relief...

Страница 13: ...from fuse cartridge 1 Use 3 4 inch and 1 2 inch wrenches to remove end plug see Figure 13 2 Use screwdriver or other tool to straighten tulip tip end of fuse link and push fuse link out of fuse cartri...

Страница 14: ...facturer s product literature for maximum interrupting ratings Internal cartridge fuse replacement 1 Verify that tank is grounded De energize transformer from a remote upstream source Ground all bushi...

Страница 15: ...n cause an explosion or fire Use a hotstick to operate transformer loadbreak equipment After operating transformer loadbreak equipment check that voltages at transformer terminals are the expected val...

Страница 16: ...clockwise to loop thru transformer open The transformer is now OPEN and the loop conductor is electrically connected 3 Move index plate between loop thru transformer open and line b only 4 Rotate swit...

Страница 17: ...e handle to desired position and allow pointer to drop into slot of index plate 5 Secure handle in its new position by tightening lock screw through index plate until it bottoms 6 Padlocking may be ac...

Страница 18: ...position as follows 1 Verify that tank is grounded De energize transformer from a remote upstream source Ground all bushings and terminals before operating dual voltage or delta wye switch 2 Back out...

Страница 19: ...Do not operate loadbreak equipment if a fault condition is suspected Doing so can cause an explosion or fire Use a hotstick to operate transformer loadbreak equipment After operating transformer load...

Страница 20: ...erly and that electrical circuit conditions are as expected Before servicing transformer secondary connected equipment verify that all transformer secondary terminals have zero voltage and ground the...

Страница 21: ...blished maximum continuous operating voltage MCOV values The transformer should not be tested impulse or applied potential with the arrester connected If connected during impulse tests the arrester wi...

Страница 22: ...by rotating handle 3 4 to 1 turn after handle has come in contact with seal gland Under oil arrester disconnection during test with out arrester disconnect switch To disconnect arresters without a dis...

Страница 23: ...nt dirt or moisture from entering the opened transformer tank Contamination of the insulating liquid will prevent the transformer from operating properly and may cause serious damage to the transforme...

Страница 24: ...aks Test pressure should not exceed 7 psig Established pressure should be main tained for at least four hours to insure that all seals are proper 4 Re install the nutguard using 25 ft lbs torque to ti...

Страница 25: ...t cover weld 10 Thoroughly clean tank cover to help prevent contamination of insulating liquid when removing cover Remove all dirt grease and moisture 11 Remove tank cover from tank Weld on tank cover...

Страница 26: ...ntenance on cabinet 2 Place one 1 4 to 3 8 inch shim directly below faceplate on both sides of tank at points A and A see Figure 28 3 Place one 1 1 2 inch wedge under each side of cabinet at points B...

Страница 27: ...nventional transformer oil mixed with R Temp fluid Conventional transformer oil content of 3 in R Temp fluid lowers the fire point below 300 C Measure the ASTM flash and fire points if the presence of...

Страница 28: ...uld be clean and dry large mouth glass bottles Make sure that the liquid being sampled is representative of the liquid in the unit Sufficient liquid must first be drawn off to ensure that the sample w...

Страница 29: ...y Cleveland Open Cup 2 ASTM D877 Standard Test Method for Dielectric Breakdown Voltage of Insulating Liquids Using Disk Electrodes 3 ASTM D923 Standard Practices for Sampling Electrical Insulating Liq...

Страница 30: ...reported and investigated Annual Cabinet Interior Maintenance Items to Inspect Points to be checked Remedial Action Frequency Gauges and Controls Check for proper operation Repair or replace damaged o...

Страница 31: ...g will achieve a rainbow coloring if a particular terminal is experiencing an over temperature condition Tighten any loose connections immediately Any damage or discoloration that is observed should b...

Страница 32: ...on com cooperpowerseries 2015 Eaton All Rights Reserved Printed in USA Publication No MN202001EN August 2015 For Eaton s Cooper Power series three phase pad mounted transformer product information cal...