Bay-O-Net fuse replacement

When replacing fuses in Flapper™ style Bay-O-Net 

fuse assembles, refer to 

Bay-O-Net Fuse Re-Fusing 

Instructions

 in this manual. Follow the same procedure as 

with conventional oil-filled transformers. 

Operation

Eaton designs its transformers to operate at rated load with 

a temperature rise equal to or less than the temperature 

rise printed on the transformer’s nameplate. Operating 

transformers in excess of IEEE Std C57.91™-2011 standard 

will result in accelerated loss of insulation system life. The 

coil insulation has been carefully made with thermally-

upgraded materials to ensure long life at rated loads. Severe 

and prolonged overloads of mineral oil-filled transformers 

will result in overheating and accelerated aging of the 

insulation, which may lead to premature failure. PEAK™ 

transformers have extended life and can be operated at 

higher temperatures. Refer to IEEE Std C57.154™-2012 

standard for details.

Mixtures of Envirotemp™ FR3™ fluid and 

conventional transformer oil 

Envirotemp™ FR3™ fluid is fully miscible with conventional 

transformer oil. There is no known detrimental performance 

impact when Envirotemp™ FR3™ fluid is mixed with 

conventional transformer oil. Conversely, except for some 

reduction in flash and fire points, the same is true for 

conventional transformer oil mixed with Envirotemp™ 

FR3™ fluid. Conventional transformer oil content of >7% 

in Envirotemp™ FR3™ fluid lowers the fire point below 

300 °C. Measure the ASTM flash and fire points if the 

presence of conventional transformer oil is suspected. If 

flash or fire points fall below the minimum values required, 

retrofilling may be required. To maintain its exceptional 

environmental classification, mixing of Envirotemp™ FR3™ 

dielectric coolant with any other fluids should be avoided.
Contact your Eaton representative for additional handling 

guidelines for Envirotemp™ FR3™ fluid.

Sampling insulating liquid

Before sampling the insulating liquid, verify that the tank 

is grounded. De-energize the transformer from a remote 

upstream source. Ground the bushings and terminals.
Refer to ASTM D923 “Standard Practices for Sampling 

Electrical Insulating Liquids” for sampling techniques.
A sample of the liquid should be taken when the liquid tem-

perature is equal to or greater than the surrounding air to 

avoid condensation of moisture on the liquid.
Containers used for sampling liquid should be clean and dry 

large mouth glass bottles. Make sure that the liquid being 

sampled is representative of the liquid in the unit. Sufficient 

liquid must first be drawn off to ensure that the sample will 

be from the bottom of the tank, and not the liquid stored in 

the sampling pipe

Testing insulating liquid

For the dielectric strength of the insulating liquids, follow 

the technique as specified by ASTM D877, “Standard Test 

Method for Dielectric Breakdown Voltage of Insulating 

Liquids Using Disk Electrodes”.
If the dielectric strength of the liquid drops below 26 kV, it 

should be filtered until it tests at 26 kV or better.

Filtering insulating liquid

Conventional transformer oil, R-Temp, or Envirotemp™ 

FR3™ fluids can be filtered by means of a filter press. 

The filter press is effective for removing all types of 

foreign matter, including finely divided carbon and small 

amounts of moisture. The purifier equipment consists of a 

specifically proportioned filter press, a positive volume gear 

pump, driving motor, combined drip pan and mixing tank, 

necessary piping, valves, strainer, gauges and drying oven. 

Follow manufacturer’s instructions for purifier equipment 

operation.
Filtration should be continued until the dielectric test of the 

insulating liquid is 26 kV or better.
When filtering R-Temp or Envirotemp™ FR3™ fluid, the 

filtering equipment must be free of contaminants and other 

liquids. The presence of other liquids may alter the physical 

and electrical characteristics of R-Temp or Envirotemp™ 

FR3™ fluid. This could result in a reduction of fire point.

Lowering insulating liquid level

1.  Verify that tank is grounded. De-energize transformer 

from a remote upstream source. Ground all bushings 

and terminals.

2.  If cover removal is required, remove cover as outlined 

in 

Tank Cover Removal and Installation

 section of 

this manual.

3.  Prepare a clean, dry storage container to receive liquid.
4.  Use pumps and hoses that have not been 

contaminated by contact with dissimilar liquids. Use a 

metal or non-rubber hose. Oil dissolves the sulfur found 

in rubber and will prove harmful to conductor material.

5.  Attach pump intake line to drain valve on transformer 

tank.

6.  Place output line nozzle on bottom of storage container. 

Do not permit liquid to splash into receiving container. 

Splashing will introduce air and moisture into liquid.

7.  Do not lower liquid below top of core clamp unless 

absolutely necessary. Exposing coils may allow 

moisture to contaminate coil insulation.

24

Three-phase pad-mounted compartmental type installation and maintenance instructions

   MN202001EN   August 2015

Содержание COOPER POWER SERIES

Страница 1: ...ER POWER SERIES Distribution Transformers MN202001EN Effective August 2015 Supersedes S210 12 1 August 2013 Three phase pad mounted compartmental type transformer installation and maintenance instruct...

Страница 2: ...NTRACT BETWEEN THE PARTIES ANY SUCH CONTRACT STATES THE ENTIRE OBLIGATION OF EATON THE CONTENTS OF THIS DOCUMENT SHALL NOT BECOME PART OF OR MODIFY ANY CONTRACT BETWEEN THE PARTIES In no event will Ea...

Страница 3: ...Loadbreak Switches 11 Tap Changer 12 Dual Voltage and Delta Wye Switch 14 Vacuum Fault Interrupter VFI 15 Air Switches Arc Strangler 16 Surge Arresters 17 MAINTENANCE Exterior Maintenance 19 Cabinet I...

Страница 4: ...ions when working around high voltage lines and equipment and support our Safety For Life mission Safety information DANGER Hazardous voltage Contact with hazardous voltage will cause death or severe...

Страница 5: ...er capacity When using a forklift lift with the transformer tank closest to the mast of the forklift since most of the transformer weight is in the tank Pallet mounted equipment may also be moved by c...

Страница 6: ...abinet the installation will not provide the security needed to prevent tampering by the public Add a permanent mortar seal to fill the gaps Pre service inspection exterior New transformers or transfo...

Страница 7: ...e on underside of the tank cover or man hole cover 2 Loose shifted or damaged parts bushings fuse holders etc 3 Broken or loose connections 4 Contaminated insulating liquid sediment or foreign objects...

Страница 8: ...ransformer nameplate Transformer neutrals must be connected to system neutrals Leads and connections that are not used must be insulated from ground and all other leads Livefront transformer connectio...

Страница 9: ...furnished with the transformer Liquid temperature gauge Transformers may be furnished with a temperature gauge as optional equipment to indicate the top liquid temperature in the tank in degrees Cels...

Страница 10: ...sformer Pressure relief device Transformers may have a cover mounted pressure relief device PRD in addition to the faceplate mounted pressure relief valve PRV standard on all three phase pad mounted d...

Страница 11: ...minals following industry accepted safe grounding practices Grounding secondary terminals protects against situations such as a standby generator energizing transformer from the secondary circuit Foll...

Страница 12: ...valve to open valve Hold the valve open for 30 seconds after pressurized air can no longer be heard hissing through the valve 2 Close pressure relief valve and wait 30 seconds 3 Pull pressure relief...

Страница 13: ...from fuse cartridge 1 Use 3 4 inch and 1 2 inch wrenches to remove end plug see Figure 13 2 Use screwdriver or other tool to straighten tulip tip end of fuse link and push fuse link out of fuse cartri...

Страница 14: ...facturer s product literature for maximum interrupting ratings Internal cartridge fuse replacement 1 Verify that tank is grounded De energize transformer from a remote upstream source Ground all bushi...

Страница 15: ...n cause an explosion or fire Use a hotstick to operate transformer loadbreak equipment After operating transformer loadbreak equipment check that voltages at transformer terminals are the expected val...

Страница 16: ...clockwise to loop thru transformer open The transformer is now OPEN and the loop conductor is electrically connected 3 Move index plate between loop thru transformer open and line b only 4 Rotate swit...

Страница 17: ...e handle to desired position and allow pointer to drop into slot of index plate 5 Secure handle in its new position by tightening lock screw through index plate until it bottoms 6 Padlocking may be ac...

Страница 18: ...position as follows 1 Verify that tank is grounded De energize transformer from a remote upstream source Ground all bushings and terminals before operating dual voltage or delta wye switch 2 Back out...

Страница 19: ...Do not operate loadbreak equipment if a fault condition is suspected Doing so can cause an explosion or fire Use a hotstick to operate transformer loadbreak equipment After operating transformer load...

Страница 20: ...erly and that electrical circuit conditions are as expected Before servicing transformer secondary connected equipment verify that all transformer secondary terminals have zero voltage and ground the...

Страница 21: ...blished maximum continuous operating voltage MCOV values The transformer should not be tested impulse or applied potential with the arrester connected If connected during impulse tests the arrester wi...

Страница 22: ...by rotating handle 3 4 to 1 turn after handle has come in contact with seal gland Under oil arrester disconnection during test with out arrester disconnect switch To disconnect arresters without a dis...

Страница 23: ...nt dirt or moisture from entering the opened transformer tank Contamination of the insulating liquid will prevent the transformer from operating properly and may cause serious damage to the transforme...

Страница 24: ...aks Test pressure should not exceed 7 psig Established pressure should be main tained for at least four hours to insure that all seals are proper 4 Re install the nutguard using 25 ft lbs torque to ti...

Страница 25: ...t cover weld 10 Thoroughly clean tank cover to help prevent contamination of insulating liquid when removing cover Remove all dirt grease and moisture 11 Remove tank cover from tank Weld on tank cover...

Страница 26: ...ntenance on cabinet 2 Place one 1 4 to 3 8 inch shim directly below faceplate on both sides of tank at points A and A see Figure 28 3 Place one 1 1 2 inch wedge under each side of cabinet at points B...

Страница 27: ...nventional transformer oil mixed with R Temp fluid Conventional transformer oil content of 3 in R Temp fluid lowers the fire point below 300 C Measure the ASTM flash and fire points if the presence of...

Страница 28: ...uld be clean and dry large mouth glass bottles Make sure that the liquid being sampled is representative of the liquid in the unit Sufficient liquid must first be drawn off to ensure that the sample w...

Страница 29: ...y Cleveland Open Cup 2 ASTM D877 Standard Test Method for Dielectric Breakdown Voltage of Insulating Liquids Using Disk Electrodes 3 ASTM D923 Standard Practices for Sampling Electrical Insulating Liq...

Страница 30: ...reported and investigated Annual Cabinet Interior Maintenance Items to Inspect Points to be checked Remedial Action Frequency Gauges and Controls Check for proper operation Repair or replace damaged o...

Страница 31: ...g will achieve a rainbow coloring if a particular terminal is experiencing an over temperature condition Tighten any loose connections immediately Any damage or discoloration that is observed should b...

Страница 32: ...on com cooperpowerseries 2015 Eaton All Rights Reserved Printed in USA Publication No MN202001EN August 2015 For Eaton s Cooper Power series three phase pad mounted transformer product information cal...

Отзывы: