6   First commissioning and modifying  network settings

Installation and Operating Instructions  Web-Controller

   40071860236 (E)   February 2019   www.eaton.com

Resistor must be connected next to the switch.

S1 CGLine

S2 Interface

Option inputs (In1/In2):

Programmable digital inputs. The inputs are activated by 

bridging of both contacts of In1 or In2.
The following functions can be freely assigned to the digital 

inputs:

 

n

Rest order

 

n

Maintained Light ON/OFF per Line

 

n

Start function test

 

n

Stop test

 

n

External failure

Relay outputs:

The  Web-Controller also has 2 freely programmable 

relay outputs each with a change-over contact.
Programmable functions:

 

n

At least one luminaire failure

 

n

Three consecutive luminaire failure

 

n

Communication failure

 

n

Battery operation

 

n

Function test active

 

n

Duration test active

 

n

Charging failure

 

n

Test failure

Assignment:

Relay 1: 

Relay 2:

21

22

24

11

12

14

USB connections:

The  Web-Controller has 2 USB connections: 1 x USB A 

host and 1 x USB B device.

USB1 (Type A host):

A standard USB storage stick can be connected to this USB 

port to save the current configuration and the logbook to the 

USB stick.

USB2 (Type B device):

This USB connection enables connection of the  

Web-Controller to a standard PC. Controller functions can be 

programmed via the PC and a configuration software, e.g. 

luminaire configurations. The PC configuration software is 

available optionally.

6    First commissioning and modifying  

network settings

The network settings of the Web-Controller can be modified 

by the PC software or via web browser. The following 

procedure describes the setup via web browser.

 

NOTE 

For correct perform of the duration test and function test the 

date and the time must be adjusted (see chapter 6.5).

6 .1   Factory default nework settings

The  Web-Controller is supplied as standard with the 

fixed IP address 192.168.1.200. Operation via DHCP (dynamic 

IP address assignment) is possible but not factory-activated.
Because typical company networks only permit own-assigned 

IP addresses, we recommend configuring network settings via 

direct connection to a PC, e.g. a notebook.

6 .2   Preparing the PC for configuration

It is mandatory to observe the following:

 

n

For direct connection from the  Web-Controller to 

a PC, a crossover cable is required.

 

n

The devices must be in the same subnet, meaning the net-

work card of the PC must be set to 192.168.1.xxx (not equal 

to 200), e.g. 192.168.1.50 (subnet to 255.255.255.0).

 

n

Settings for gateway and DNS must not be taken into 

account with a direct connection.

Connection example for direct connection: 

PC network setting:

To modify the network settings of the PC open the system 

control  

 Network and release centre  

Содержание CGLine+ Web-Controller

Страница 1: ...Installation and Operating Instructions CGLine Web Controller Target group Electrical specialists CGLine Web Controller...

Страница 2: ...EENS 13 7 1 Home start screen 13 7 2 Start screen after registration 14 7 3 Overview of all faulty luminaires complete overview 15 7 4 Overview of all faulty luminaires for each zone 16 7 5 Overview o...

Страница 3: ...lines with max 200 luminaires each or 2 lines with max 400 luminaires each only with homogeneous installation of CGLine luminaires CGVision software Configuration and full visualisation of 32 x 800 N...

Страница 4: ...policies O O Restrict Network Access Ideally CGLine Web Controller should be installed on a segregated network However when the CGLine Web Controller is connected to a wider network make sure that the...

Страница 5: ...technical regulations when setting up and operating electrical operating equipment 5 1 Assembly Observe impermissible temperatures at the installation loca tion during mounting The permissible ambient...

Страница 6: ...ctional method O O Press the service pin 1 sec but 3 sec function test started for all luminaires O O Press the service pin 6 sec only new luminaires search started 1 6 7 8 9 10 2 3 4 5 3 Push buttons...

Страница 7: ...Table 3 Cable length line Cross section Length Total lines 0 5 qmm 260 m 660 m 1 0 qmm 520 m 1320 m 1 5 qmm 800 m 2000 m Table 4 Electrical data line Power supply bus 25 V Max permissible voltage drop...

Страница 8: ...tandard PC Controller functions can be programmed via the PC and a configuration software e g luminaire configurations The PC configuration software is available optionally 6 First commissioning and m...

Страница 9: ...displayed Mark the entry Internet protocol version 4 1 then continue with Properties 2 Usually the network card is on DHCP i e Automatically reference IP address Modify the entry to Use the following...

Страница 10: ...o the address bar The start screen of the CGLine Web Controller opens The screen shows an over view of the installed CGLine system with sum status information To have access to the submenus a login 1...

Страница 11: ...tion 1 It is possible to change the network settings 1 6 5 Modifying of the language date and time To change the language to English please click on Configuration 1 in the register General 2 The langu...

Страница 12: ...via the names is possible The CGLine Web Controller is supplied with a factory set static IP address of 192 168 1 200 3 Operation via DHCP is possible but in this case it is recommended to select sta...

Страница 13: ...s User Admin Password EATON User User Password GUEST 1 The Admin Account allows full access to the CGLine Web Controller e g start function test The User account allows only access for monitoring the...

Страница 14: ...Yellow min 1 luminaire faulty O O Red min 3 luminaires faulty e g lamp failure After the login the navigation menu appears on the left side 1 O O Home The start screen is accessed via Home at any time...

Страница 15: ...ible to enter to the building layout picture if it is pre The menu Oveview 1 and the tab Overview luminaire failure 2 display all luminaires with a fault 3 O O L line no 1 4 O O Z zone 2 16 O O B lumi...

Страница 16: ...er 40071860236 E February 2019 www eaton com 7 4 Overview of all faulty luminaires for each zone All luminaires with a fault in a zone are displayed in the Overview menu 1 and the Zone tab 2 Via the d...

Страница 17: ...erview luminaires 2 shows all installed luminaires on the CGLine Web Controller 1 2 7 6 Information information text of the luminaires This screen shows the name with max 20 characters and information...

Страница 18: ...f luminaires addresses For changing the configuration of luminaires addresses please follow the steps below 1 Click on the tab Luminaires The table with all the luminaires installed appears 2 Click on...

Страница 19: ...uration tests are aborted O O Switch maintained mode ON OFF Luminaires in main tained mode L applied can be switched ON or OFF if luminaire supports this function O O Update luminaire status Actualisi...

Страница 20: ...st times On the Test tab 2 in the configuration menu 1 it is possible to determine start times for a function test and duration test for up to 8 groups It is also possible to set a test interval via w...

Страница 21: ...mode luminaires of the line as long as the input is active O O Start function test With positive pulse starts the function test with all luminaires O O Stop FT DT Interrupts a duration test or functi...

Страница 22: ...ally correct it is necessary after the commissioning to correctly set the date and 2 1 4 5 3 7 13 Network settings Follwing settings are possible O O DHCP Dynamic Host Control Protocol if a DHCP is in...

Страница 23: ...plete logbook is downloadable via log book dat This file is only usable with the CGLine PC software see manual CGLine PC software The CGLine Web Controller contains an integrated e mail client 1 that...

Страница 24: ...layouts of the building or areas It is possible to import up to 30 building layout plans with max 200 luminaires each The colour of the luminaire shows the status e g red luminaire failure To use this...

Страница 25: ...ding layouts can displayed now by the folder List of building layouts 1 With click on the name of the layout which is dis played as hyperlink with xml extension 2 the lay out can load from the con tro...

Страница 26: ...n there is a search func tion 1 2 This enables quickly finding any defective luminaires in a building To find a luminaire in the layout plan the line the zone and the luminaire to address can be selec...

Страница 27: ...e entered here After con firming via Add the devices are automatically created A device can be deleted from the list again via Delete 3 3 1 2 7 24 Overview all Web Controller With several installed CG...

Страница 28: ...ght solution for the application But decision makers demand more than just innovative products They turn to Eaton for an unwavering commitment to personal support that makes customer success a top pri...

Отзывы: