Eaton BladeUPS 5 kVA to 60 kVA (N+1) User’s Guide 164201649—Rev 14
67
Figure 48. Attaching the Front Rail
Position 1
Front M5 Screws
Position 12
Rail Stud
(2 places)
Position 2
Position 11
4.
Adjust the rail size on the rail assembly for the depth of your rack.
5.
Secure the rail to the rear of the rack with four M5 machine screws and clip or cage nuts.
NOTE
Verify that the holes in the rail align properly with the hole pattern in the rack. If the rack
has square holes, verify that the stud on the end of the rail aligns within the square hole.
Figure 49. Securing the Rear Rail (Right Rail Assembly Shown)
Position 2
Position 7
Position 8
Position 1
Bottom of Rack
or Top of Other
Cabinet
Rear M5 Screws
Cage Nuts
Position 4
Rail Stud
6.
Tighten all screws at the front and rear of the rail, then tighten the rail adjustment screws.
Leave the screws through the hold-down brackets loose.
7.
Repeat Steps 3 through 6 for the other rail.
Содержание BladeUPS none
Страница 8: ...viii Eaton BladeUPS 5 kVA to 60 kVA N 1 User s Guide 164201649 Rev 14 Table of Contents ...
Страница 12: ...xii Eaton BladeUPS 5 kVA to 60 kVA N 1 User s Guide 164201649 Rev 14 List of Figures ...
Страница 14: ...xiv Eaton BladeUPS 5 kVA to 60 kVA N 1 User s Guide 164201649 Rev 14 List of Tables ...
Страница 20: ...6 Eaton BladeUPS 5 kVA to 60 kVA N 1 User s Guide 164201649 Rev 14 Introduction ...
Страница 134: ...120 Eaton BladeUPS 5 kVA to 60 kVA N 1 User s Guide 164201649 Rev 14 Metering ...
Страница 160: ...16420164914 164201649 14 ...