44
UPS 225 - 275 kVA/300kVAPF0.8
1027212
User’s and Installation Guide
Revision E
4.9 Installing options, accessories, and distributed bypass
control wiring
To install options, accessories, and distributed bypass control wiring, see Chapter 5: “Installing options
and accessories”.
4.10 Initial startup
Startup and operational checks must be performed by an authorized Eaton Customer Service Engineer,
or the warranty terms specified on page 124 become void. This service is offered as part of the sales
contract for the UPS. Contact service in advance (usually a two-week notice is required) to reserve a
preferred startup date.
4.11 Completing the installation checklist
The final step in installing the UPS system is completing the installation checklist at the end of this
manual. This checklist ensures that you have completely installed all hardware, cables, and other
equipment. Complete all items listed on the checklist to ensure a smooth installation. Make a copy of
the installation checklist before filling it out, and retain the original. If installing a parallel system,
complete the parallel system installation checklist in addition to the installation checklist.
After the installation is complete, your service representative must verify the operation of the UPS
system and commission it to support the critical load. The service representative does not perform any
installation tasks other than verifying software and operating setup parameters. Service personnel may
request a copy of the completed installation checklist to verify all applicable equipment installations
have been completed.
NOTE
The installation checklist MUST be completed prior to starting the UPS system for the first time.