Installation, Operation and Parts Manual
EE-6214EKZ
14
Step 6: Erect and secure the post.
1. Make the posts face to each other and the distance between the posts equals to the length of the crossbeam. Use proper means to erect
the post.
2. Use suitable means to raise the lifting carriage to the first latching position. All the mounting holes in the base plate are then accessible.
Make sure the locking pawl is engaged.
3. Check and align the position of the base plates again.
4. Drill the mounting holes, using D18 carbide tipped masonry drill bit. Remove the drilling dust from the hole.
5. Use a spirit level to check the vertical alignment of the posts. If necessary, place equalizing plates under the base plates.
6. Impact and drive anchoring bolt into hole until nut and washer contact base.
Tighten the nuts with torque wrench to 80-100Nm.
Anchoring bolt
A1
(foundation thickness )
A2
(drilling depth)
A3
(anchoring depth)
M18x200
≥200mm
160mm
145mm
Step 7: Connect steel cables.
1. Route and fix according to the following diagram of steel cable connection.
2. Use suitable means to raise carriages at both sides to the first latching point. Ensure the both carriages are locked.
3. After the cable being fixed, adjust and make the cables at both sides be with the same tightness. (This could be judged by the sound
caused by mechanical safety locking system during lifting process.)
4. Grease with NO.1 lithium grease (It is a must.)
Содержание EE-6214EKZ
Страница 10: ...Installation Operation and Parts Manual EE 6214EKZ 10 3 4 Dimensions...
Страница 27: ...Installation Operation and Parts Manual EE 6214EKZ 27 Annex 2 Electrical schemes and parts list...
Страница 28: ...Installation Operation and Parts Manual EE 6214EKZ 28...
Страница 29: ...Installation Operation and Parts Manual EE 6214EKZ 29...