background image

11

necessary.  The Firestop Radiation Shield will 

fit inside the Attic Insulation Shield.  

b.

  Assemble Chimney Sections until at least 

18 inches of chimney extends above the 

Firestop Radiation Shield.  

c.

  Slip the Insulation Shield over the Chimney 

and Firestop Radiation Shield until the base 

sits squarely on the framed opening. 

(Figure 

7)

.

d.  Nail the Insulation Shield to the top of the 

framed opening with at least two 8-penny nails 

per side.  

(Figure 12)

.  

e.

  Wrap the Collar around the chimney and 

fasten it loosely.  Slide the Collar down to meet 

the Insulation Shield.  Slip the tab through the 

adjacent slot and fold it back to tighten the 

Collar. 

(Figure 13)

9.  Attach Flashing:

 In new construction, 

assemble the Chimney Sections to a point  

above the roof, then slip the Flashing over 

the chimney.  On an existing roof, center 

and install the Flashing before extending 

the chimney above the roof.  Allow space 

to permit sliding the next Chimney Section 

up through the Flashing.  Always insure the 

chimney remains vertical, and that at least a 

2-inch clearance to combustible materials is 

maintained all around.  Install the upper edge 

of the Flashing under the roofing.  Nail to the 

roof along the upper edge and the upper half 

on each side with 1-inch roofing nails.  Do 

not nail the lower edge of the Flashing, or the 

lower half of the sides. 

(Figure 14)

.  Seal all 

nail heads with a non-hardening waterproof 

sealant.  On flat or tarred and graveled roofs, 

nail and seal the Flat Roof Flashing to the roof 

on all sides with roofing compound.  Do not put 

screws through the Flashing into the Chimney 

Pipe.

10.  Finish Top:

 Apply a non-hardening 

waterproof sealant around the chimney at the 

point where the Storm Collar will meet the 

Figure 12

WARNING: IF CHIMNEY 

IS ENCLOSED IN ATTIC 

AREA, YOU 

MUST

 USE 

VENTILATED FLASHING.

SDP-IS

Figure 13

Figure 14

1 INCH ROOFING 

NAILS ALONG TOP OF 

FLASHING

PUSH COLLAR 

DOWN TO 

FLASHING AND 

SEAL WITH 

NON-HARDENING 

SEALANT. 

(SEALANT SHOWN 

IN HEAVY LINE)

STORM COLLAR

SDP-SC

FLASHING

SDP-F

SDP-TF

Содержание duraplus

Страница 1: ...DuraPlus All Fuel Chimney System Installation Instructions...

Страница 2: ...manufacturer s warranty and may have an effect on your homeowner s insurance and UL listing status Keep these instructions for future reference This booklet also contains instructions for installing a...

Страница 3: ...7 Offset Elbow Installation 12 Offset Chart 13 Extended Roof Bracket Installation 14 Roof Supported Installations 15 Tee Supported Installations 16 Masonry Fireplace Installations 18 Zero Clearance Fi...

Страница 4: ...ct your local Building Official or Fire Official regarding permits restrictions and installation inspections in your area DuraPlus APPLICATIONS Use DuraPlus with wood stoves fireplaces furnaces boiler...

Страница 5: ...building within ten feet Figure 1 DuraPlus may be installed up to 35 feet high If a chimney is installed higher than 35 feet a supporting Elbow Strap must be placed every 8 feet If the chimney extend...

Страница 6: ...elow pertain to all stoves or other appliances installed with DuraPlus chimney systems Choice Choose a stove that is listed by a recognized testing laboratory is appropriate for your needs and is not...

Страница 7: ...and mark this center point on the ceiling Refer to Table 2 for specific framing and clearance dimensions Mark appropriate cutting lines around the center point Cut a square hole in the ceiling for a...

Страница 8: ...passes through additional floors and ceilings install Firestop Radiation Shields Where the chimney passes through an attic Firestop Radiation Shields and Insulation Shields must be installed 4 Frame O...

Страница 9: ...tibles is not required when the chimney passes through Close Clearance Shields When using Close Clearance Shields Ventilated Flashing must be installed Refer to Figure 10 which pictures both Ventilate...

Страница 10: ...outer liner 8 Install Attic Insulation Shield Install the Attic Insulation Shield where the chimney passes into an attic It s purpose is to prevent debris and insulation from getting too close to the...

Страница 11: ...ermit sliding the next Chimney Section up through the Flashing Always insure the chimney remains vertical and that at least a 2 inch clearance to combustible materials is maintained all around Install...

Страница 12: ...t furnished by DuraVent 11 Enclosures Enclose chimneys where they pass through occupied spaces including closets Always maintain at least a 2 inch clearance between the chimney and any combustible sur...

Страница 13: ...s band around the angled portion of the top Elbow then tighten the nut and bolt until the clamp is firm Wrap the Elbow Strap end over an adjacent joist or rafter and secure it with at least two 8 pen...

Страница 14: ...il heads carefully with a non hardening waterproof sealant 3 Attach Conduit Flatten 1 inch and drill a 1 4 inch hole at each end of both pieces of conduit Bolt each conduit to the Pipe Band and Roof B...

Страница 15: ...from combustibles etc 2 Cut Openings Cut a roof opening directly above the appliances flue outlet collar just as in a Ceiling Supported Installation Steps 1 thru 5 If a separate ceiling and roof exis...

Страница 16: ...e s flue outlet collar For new construction prior to sheetrock or other covering of the wall studs is applied frame a square opening between the studs as specified in Table 2 Figure 25 Should it be ne...

Страница 17: ...tion of wall thimble sdp wt black outside view from outside Figure 27 note if system exits thru wall into garage an enclosure isrequired ventilated flashing must be used 2 inches minimum enclosure GAR...

Страница 18: ...enclosure has been constructed installing the chase cover requires some special considerations The chase must be ventilated at the top and a 1 2 inch air gap must be established between the cover and...

Страница 19: ...10 Refer to Figure 1 and Table 4 for chimney height requirements Always maintain at least 2 inches of clearance to combustible materials and enclose the chimney where it passes through occupied areas...

Страница 20: ...20 Table 4...

Страница 21: ...ip connector slips into the hole in the ceiling support or wall thimble Align the tabs on the slip connector with the notches in the face of the support or wall thimble push the connector in and twist...

Страница 22: ...leaning unscrew the four screws that attach the cap s support legs to the cap base The Tee Cleanout Cap can be removed once the screws are unscrewed Remember to replace the cap when you are finished c...

Страница 23: ...23...

Страница 24: ...case of a chimney fire the chimney must be inspected and approved by a certified Chimney Sweep before reuse After each annual inspection maintenance and cleaning the certified Chimney Sweep must fill...