Fig. 3.11 Electrical requirements
3.2.3. Charging Procedure
Failure to follow the listed points may cause
injury or death
1. Before use, check the cable for damages.
Damaged cables must not be used.
2. Each charging cable must be plugged in a
secured charging socket. The use of multi-plugs
is not allowed.
3. Check the charging socket at the container for
damages. In case of damages, the socket must
not be used.
4. Observe the electrical preconditions,
see label on the charging socket.
5. Remove the charging cable before moving the container
DoKaSch recommends the use of the original charging cable. If other cables are used, the
requirements on the label at the charging socket (fig.3.6) must be observed. DoKaSch accepts no
liability for damages when using external cables or failure to comply with the requirements.
1.
Open the charging socket cover.
2.
Connect the blue CEE industry plug with
the blue charging socket.
3.
Connect the charging cable to a suitable
power supply. Observe the electrical
requirements, see label on the charging
sockets cover (Fig. 3.6).
4.
When the container is switched on, the
message "Charging“ appears on the display
after 30 seconds as well as the charging flash
in the battery symbol (Fig. 2.20 ).
If the container is switched off before the cable
will be plugged in, it will switch on automatically
after plugging in.
The “Charging” message and
the charging flash appear once the container is
completely booted.
Fig. 3.12 CEE coupling charging unit