30
999801002 - 02/2017
Anchoring on the structure
User Information
Automatic climbing formwork Xclimb 60
Anchoring on the structure
Positioning point and suspension
point
▪
Universal climbing cone 20.0
- The positioning point and the suspension point
are both prepared using this one single type of
cone
▪
Stop anchor 20.0
- Expendable anchoring component for anchoring
the Universal climbing cone (and thus the climb-
ing unit) in the concrete from one side.
▪
Cone screw B 7cm
- On the positioning point - for fastening the Uni-
versal climbing cone.
- On the suspension point – for safe fixing of the
Guiding shoe Xclimb 60 rigid and thus of the
whole climbing unit.
▪
Guiding shoe Xclimb 60 rigid
- Provides guidance during repositioning, and
load-transfer.
Types of stop anchor
Note:
In the project planning stage and later,
avoid mixing
different types of stop anchor
to exclude the risk of
confusion on the jobsite.
Stop anchor 20.0 17.5cm 55
a ... Tie-rod length: 17.5
cm
b ... Installation depth: 23
cm
c ... Minimum wall thickness:
25
cm
(where the concrete cover is 2
cm)
c ... Minimum wall thickness: 26
cm
(where the concrete cover is 3
cm)
d ... Concrete cover
e ... Size of stop anchor plate: 55
mm
Stop anchor 20.0 11.5cm 90
a ... Tie-rod length: 11.5
cm
b ... Installation depth: 17
cm
c ... Minimum wall thickness: 19
cm
(where the concrete cover is 2
cm)
c ... Minimum wall thickness: 20
cm
(where the concrete cover is 3
cm)
d ... Concrete cover
e ... Size of stop anchor plate: 90
mm
☞
Important note:
Use only the
Tie rod system 20.0
with Doka
automatic climbing formwork.
Risk of confusion!
➤
If Doka automatic climbing formwork is being
used jointly with other Doka climbing sys-
tems, then the Tie rod system 20.0 must be
used throughout the entire project.
A
Universal climbing cone 20.0
B
Sealing sleeve K 20.0 (expendable anchoring component)
C
Stop-anchor 20.0 (expendable anchoring component)
D
Depth mark
E
Cone screw B 7cm
F
Guiding shoe Xclimb 60 rigid
F
C
D
B
A
E
98010-388-01
WARNING
The short
Stop anchor 20.0 11.5cm
90
has a
much lower load-bearing capacity than the
Stop anchor 20.0 17.5cm
55.
➤
For this reason, the short stop anchor is only
allowed to be used on systems with low ten-
sile loads at the anchoring location, such as
on climbing systems inside shafts.
➤
If the geometry means that it is only possible
to install the short stop anchor, then revised
static calculation, with extra reinforcement
steel, is required in cases where larger ten-
sile loads may occur.
➤
The Stop anchor 20.0 11.5cm
90
is
only
per-
mitted for wall thicknesses <
25
cm.
For
wall
thicknesses
25
cm, the Stop anchor 20.0
17.5cm
55 (or larger) must be used.
98071-350-20
a
b
d
c
e
98071-355-01
a
b
d
c
e
Содержание Xclimb 60
Страница 2: ...2 999801002 02 2017 User Information Automatic climbing formwork Xclimb 60 ...
Страница 9: ...User Information Automatic climbing formwork Xclimb 60 Introduction 9 999801002 02 2017 ...
Страница 29: ...User Information Automatic climbing formwork Xclimb 60 Structural design 29 999801002 02 2017 ...
Страница 79: ...User Information Automatic climbing formwork Xclimb 60 Assembly 79 999801002 02 2017 ...
Страница 87: ...User Information Automatic climbing formwork Xclimb 60 Assembly 87 999801002 02 2017 ...
Страница 127: ...User Information Automatic climbing formwork Xclimb 60 Component overview 127 999801002 02 2017 ...