5.2
Check points before commissioning
5.2.1.
Preparing the boiler for commissioning
WARNING
Do not put the boiler into operation if the supplied gas is
not in accordance with the approved gas types.
Preparatory procedure for boiler commissioning:
4
Check that the gas type supplied matches the data shown on the
boiler's data plate.
4
Check the gas circuit.
4
Check the hydraulic circuit.
4
Check the water pressure in the heating system.
4
Check the electrical connections to the thermostat and the other
external controls.
4
Check the other connections.
4
Test the boiler at full load. Check the setting of the gas/air ratio
and, if necessary, correct it.
4
Test the boiler at part load. Check the setting of the gas/air ratio
and, if necessary, correct it.
4
Finalizing work.
MCA 15 - MCA 25 MCA 25/28 MI
5. Start-up
29/04/2010 - 300022146-001-B
63
Содержание Innovens MCA 15
Страница 7: ...29 04 2010 300022146 001 B 5...
Страница 141: ...MCA 15 MCA 25 MCA 25 28 MI 9 Spare parts 29 04 2010 300022146 001 B 139...
Страница 142: ...9 Spare parts MCA 15 MCA 25 MCA 25 28 MI 140 29 04 2010 300022146 001 B...
Страница 143: ......