3.2  Bus Cabling

3.2.1 EMC Precautions

The following EMC precautions are recommended to achieve
interference-free operation of the BACnet network.
Additional EMC information is available in the 

VLT

®

 HVAC

Drive Design Guide, MG.11.Bx.yy

. Please also consult the

BACnet master manual for further installation guidelines.

Ensure compliance with relevant national and local
regulations, for example in protective earth connection.

3.2.2 Single Ground Shielding

For installing the bus cable on MS/TP, two different
strategies can be followed, Single ground of shield and
multiple ground of shield. Each strategy has both
advantages and disadvantages. The following chapter
explains the different between the two strategies. The single
ground shield is specified in the ANSI/ASRAHE 135-2004
standard. The solution benefits by having only one ground
connection of the shield, by doing so the possibility for
ground loop of equalizing current is heavily reduced. In
these systems the shield of the MS/TP cables has to be
isolated from ground at all stations, except one. At each
station the shield from the two cables has to be connected
with each other, and isolated from ground. The best solution
for this has been proven to be the use of shrink tubes. The
single ground shielding is a good approach where the
system uses long bus cables. If two buildings have to be
connected over the same MS/TP bus cable, the use of fibre
optic has to be considered. This will prevent that a lightning
stroke will be carried from one building to another, and
problem with difference in earth potential can be neglected.

3.2.3 Multiple Ground Shielding

If the distance between the individual drives is limited (e.g.
inside a cabinet or in one control room) Danfoss
recommends connecting the screen to ground at both ends
of the bus cable. This ensures the maximum protection from
EMC noise. Connecting the screen at each end will require
that each BACnet device has the same earth potential or an
equalizing current will flow in the screen of the cable and
cause disturbance and poor performance of the system. Low
impedance to ground connection of the screen can be
achieved by connecting the surface of the screen to ground,
by means of a cable clamp or a conductive cable gland. The
FC 100 Series supplies various clamps and brackets to enable
a proper ground connection of the BACnet cable screen.

Danfoss recommends to connect the screen to ground at
both ends of the bus cable. This ensures the maximum
protection from EMC noise. Connecting the screen at each
end will require that each BACnet device has the same earth
potential or else an equalizing current will flow in the screen
of the cable and cause disturbance and poor performance of
the system. Where this is not possible, the screen can be
isolated from the chassis of the drive by use of shrink-tubing.
It must be pointed out that the routing of the BACnet cable
must be established with a maximum distance to other
cables such as mains, motor cable, etc.

How to Install

VLT

®

 HVAC Drive Native BACnet Operating Instructions

10

MG.14.C1.02 - VLT

®

 is a registered Danfoss trademark

3

3

Содержание Native BACnet VLT HVAC Drive

Страница 1: ...MAKING MODERN LIVING POSSIBLE Operating Instructions Native BACnet VLT HVAC Drive...

Страница 2: ...10 4 How to Configure the System 11 4 1 Configuring BACnet 11 4 2 Example of a simple setup of BACnet 12 5 BACnet Objects 13 5 1 Feedback to Network 20 5 2 BIBBs 20 6 Parameters 22 6 1 Parameter Over...

Страница 3: ...notify former or present users of such revisions or changes 1 1 2 Safety Note Safety Regulations 1 The frequency converter must be disconnected from mains if repair work is to be carried out Check tha...

Страница 4: ...s been stopped may start if faults occur in the electronics of the frequency converter or if a temporary overload or a fault in the supply mains or the motor connection ceases 1 1 3 Symbols Symbols us...

Страница 5: ...rent and short circuit protection Selection of power cables mains motor brake loadsharing and relay Grid configuration grounded delta transformer leg IT TN etc Safety of low voltage ports PELV conditi...

Страница 6: ...vice Requests it must be able to initiate Conformance Class 6 requires 21 types of Service Requests of the 32 overall to be implemented of which 20 must be initi able and 17 executable Conformance Cla...

Страница 7: ...11 Dx yy Operating Instructions VLT HVAC Drive LonWorks MG 11 Ex yy Operating Instructions VLT HVAC Drive Metasys MG 11 Gx yy Operating Instructions VLT HVAC Drive FLN MG 11 Zx yy Output Filter Desig...

Страница 8: ...repeater is a node in both of the two segments it connects The number of frequency converters is based on a single master system If there are two or more devices e g PC tools Routers the number of fr...

Страница 9: ...requency converter 2 Connect the cable screen as described under chapter Bus Cabling NOTE Screened twisted pair cables are recommended to reduce noise between conductors 3 1 3 Network Termination 130B...

Страница 10: ...e when operating the switches The switches must not be operated with power on the frequency converter 130BT310 10 1 2 N O VLT BUS TER OFF ON A53 A54 U I U I 3 1 5 Cable Routing The BACnet communicatio...

Страница 11: ...hat a lightning stroke will be carried from one building to another and problem with difference in earth potential can be neglected 3 2 3 Multiple Ground Shielding If the distance between the individu...

Страница 12: ...ding on the system and each device connected to the BACnet MS TP must have a unique adress on this MS TP network Please also see section Parameter Overview Parameter List Parameter Default Value Setti...

Страница 13: ...eed Set the following parameters Parameter Value 8 30 Protocol BACnet 5 8 31 Address 20 8 32 Baud Rate 38 400 Baud 4 8 50 Coasting Select Bus 1 8 70 BACnet Device Instance 1025 8 72 MS TP Max Masters...

Страница 14: ...1676 MCB 101 AI 4 Analog In X42 1 1830 V MCB 109 AI 5 Analog In X42 3 1831 V MCB 109 AI 6 Analog In X42 5 1832 V MCB 109 Table 5 1 Analog Inputs Object Map ID Object_Name Present_Value Default name Pa...

Страница 15: ...14 AV 15 Motor Thermal 1618 AV 16 Reserved for VFD profile AV 17 AV 18 AV 19 AV 20 AV 21 Operating Hours 1500 Hours AV 22 Running Hours 1501 Hours AV 23 kWh Counter 1502 kWh AV 24 Motor Voltage 1612 V...

Страница 16: ...it 2096 NONE x Table 5 3 Analog Values 1 Either AV 1 or AV 2 controls the drive reference Only one of them can control the frequency converter at a time and BV 2 decides which one 2 This value is not...

Страница 17: ...exceeded External Fault 12 142 External fault has been activated in the inverter This is a hard fault that must be reset Operator Interface Error 13 Inverter programming or operational interface malf...

Страница 18: ...ved for P1660 x MCB 115 Table 5 5 Binary Inputs ID Object_Name Present_Value Default name Parameter Bit number Writeable Cmd able Timeout Option BO 0 Digital Output Term 27 590 0 x x x BO 1 Digital Ou...

Страница 19: ...for VFD profile BV 8 BV 9 BV 10 BV 11 BV 12 BV 13 BV 14 BV 15 BV 16 BV 17 BV 18 BV 19 BV 20 BV 21 Warning x x STW 7 BV 22 Trip x x STW 3 BV 23 Triplock STW 6 BV 24 Coasting CTW 3 x x x BV 25 CW CCW C...

Страница 20: ...110 3 MCO 104 BV 39 Reserved for ECB MCO 104 3110 bit 4 10 BV 40 BV 41 BV 42 BV 43 BV 44 BV 45 5 1 3 Multi state Value Objects ID Object_Name Present_Value Timeout Default name Parameter Bit number Wr...

Страница 21: ...pon control of the frequency converter can be programmed in 8 50 Coasting Select to 8 56 Preset Reference Select 8 01 Control Site overrules the settings in parameters 8 50 to 8 56 and Terminal 37 Saf...

Страница 22: ...tocol Revision X Services Supported X Object List X Max APDU Length X Segmentation Support X Local Time X Local Date X APDU Timeout X Number APDU Retries X Max Master X Max Info Frames X Device Addres...

Страница 23: ...gic OR 3 0 3 5 8 54 Reversing Select Logic OR 3 0 3 5 8 55 Set up Select Logic OR 3 0 3 5 8 56 Preset Reference Select Logic OR 3 0 3 5 8 70 BACnet Device Instance 1 1 4194304 8 72 MS TP Max Masters 1...

Страница 24: ...Visible String VisStr 33 Normalized value 2 bytes N2 35 Bit sequence of 16 boolean variables V2 54 Time difference w o date TimD See the frequency converter Design Guide for further information about...

Страница 25: ...selected in 8 04 Control Timeout Function will then be carried out In BACnet the following variables will trigger the Control Word Time parameter Analog Outputs Binary Outputs AV0 AV1 AV2 8 03 Contro...

Страница 26: ...naround delays 8 36 Maximum Response Delay Range Function Size related 11 10001 ms Specify the maximum permissible delay time between transmitting a request and receiving a response Exceeding this del...

Страница 27: ...ia the fieldbus serial communication port OR via one of the digital inputs 8 56 Preset Reference Select Option Function Select control of the frequency converter Preset Reference selection via the ter...

Страница 28: ...and warnings please refer to VLT HVAC Drive Design Guide Warnings All warnings within the frequency converter are represented by a single bit within a Warning Word A Warning Word is always an action...

Страница 29: ...supply fault 04000000 Brake resistor short circuit 08000000 Brake chopper fault 10000000 Option change 20000000 Drive initialised 40000000 Safe Stop 80000000 Not used 16 91 Alarm Word 2 Bit Hex Alarm...