Commissioning
Installer reference guide
140
ERLA EHFZ03S18DJ3V
Daikin Altherma 3 R F
4P596821-1A – 2020.05
NOTICE
ALWAYS complete the refrigerant piping of the unit before operating. If NOT, the
compressor will break.
10.3 Checklist before commissioning
After the installation of the unit, first check the items listed below. Once all checks
are fulfilled, the unit must be closed. Power-up the unit after it is closed.
You read the complete installation instructions, as described in the
installer reference
guide
.
The
indoor unit
is properly mounted.
The
outdoor unit
is properly mounted.
The following
field wiring
has been carried out according to this document and the
applicable legislation:
▪
Between the local supply panel and the outdoor unit
▪
Between indoor unit and outdoor unit
▪
Between the local supply panel and the indoor unit
▪
Between the indoor unit and the valves (if applicable)
▪
Between the indoor unit and the room thermostat (if applicable)
The system is properly
earthed
and the earth terminals are tightened.
The
fuses
or locally installed protection devices are installed according to this document,
and have NOT been bypassed.
The
power supply voltage
matches the voltage on the identification label of the unit.
There are NO
loose connections
or damaged electrical components in the switch box.
There are NO
damaged components
or
squeezed pipes
on the inside of the indoor and
outdoor units.
Backup heater circuit breaker
F1B (field supply) is turned ON.
There are NO
refrigerant leaks
.
The
refrigerant pipes
(gas and liquid) are thermally insulated.
The correct pipe size is installed and the
pipes
are properly insulated.
There is NO
water leak
inside the indoor unit.
The
shut-off valves
are properly installed and fully open.
The
stop valves
(gas and liquid) on the outdoor unit are fully open.
The
air purge
valve is open (at least 2 turns).
The
pressure relief valve
purges water when opened. Clean water must come out.
The
domestic hot water tank
is filled completely.
Содержание ERLA03DAV3
Страница 1: ...Installer reference guide Daikin Altherma 3 R F ERLA03DAV3 EHFZ03S18DJ3V...
Страница 182: ...1 7 Field settings table 6 8 2 ID9E51 Applicable units EHFZ03S18DJ3V Notes 4P596829 1 2019 10...
Страница 189: ......
Страница 190: ......
Страница 191: ......
Страница 192: ...4P596821 1A 2020 05 Copyright 2019 Daikin Verantwortung f r Energie und Umwelt...