HV Breakout Module – Mounting and installation
Installation Manual
21
Version 01.20 // 2021
4.3.3.6 Tighten the PG glands and close the housing
"
Reinsert the spring into the PG gland, attach the pressure screw to the thread and
tighten it by hand (Fig. 4-9).
"
Tighten the pressure screw using the specified torque.
"
Please observe the manufacturer's assembly instruction or the specified maximum
tightening torques in Tab. 4-1 and the note below that table.
"
HV BM 1.1: Reinsert the green inner cover.
11
Fig. 4-21: HV BM 1.2, housing closed and HV cable mounted
↻
↻
↻
↻
↻
↻
↻
↻
↻
↻
↻
↻
"
Place the cover on the housing.
NOTE!
i
To avoid water ingress, condensation, etc., special care must be taken to
ensure the tightness of the housing. CSM provides a sealing cord as spare
part. This should be changed e.g. if it is brittle or fragile or has been pinched.
"
Make sure that cover and seal are properly fitted.
"
Make sure that PG glands and HV power cables are properly mounted.
"
Fix the cover using the four or six Allen screws (
↻
) and tighten them crosswise.
11 Applies only to HV BM 1.1, hardware revision A.