Safe-Lec 2 Conductor Bar Manual
17
SECTION 6 - BOLTED STEEL/COPPER JOINT ASSEMBLY
Tools Needed
• 10mm A/F open ended wrench
Bolted Steel/Copper Joint Installation
1. Fit bolt into joint plate (ensure tab captivates the head on the setscrew).
2. Slide bolt and joint plate into conductor bar ends.
3. Place joint over bolt, making sure alignment mark is in line with end faces of conductor bar.
4. Fit washer and nut onto bolt in the order shown.
5. Tighten nut to recommended torque of 8 Nm (5-6 ft-lbs).
6. Check that both faces of the conductor bar are touching each other and there is no gap exceeding 0.5mm (0.02”) at the faces.
NOTE
• If the conductor was field cut, file off all burrs on conductor ends before assembling splices.
Figure 17-1
1. Nut
2. Washer
3. Joint
4. Bolt
5. Joint Plate
6. Conductor Bar
7. Alignment Mark
1
3
2
4
5
6
7