background image

 

5. 

Mechan

ica
l Installati

on

 

Mechanical Installation 

Prior to Installation 

Read the relevant parts of this manual and make sure you have the following information: 

 

All necessary approvals to work on the site 

 

The OPT factory set up sheet 

 

The site audit document 

 

The telephone number, user name and password for ADSL sites 

 

Contact details for site owner or manager 

 

Contact details for help desk 

 

NOTE: 

For ADSL sites, check that either the broadband account is set up. 

NOTE: 

For wireless sites check that the SIM card is registered to a valid account. 

NOTE:

 It is advisable to book an installation time with the help desk at least 24 hours before 

going to site. This will ensure that help desk staff will be prepared for your inquiries. Help 
desk hours are currently Monday to Friday 7.30am to 7pm NZ Standard Time. 

Bring the following equipment: 

 

Mechanical and electrical tools 

 

Multimeter 

 

Fastenings to mount the OPT 

 

Security key drivers (Security TORX or unique security key if Extra Security equipped) 

 

A fully charged laptop computer 

 

A charged cell phone 

 

OPT spares kit 

 

SIM cards for wireless sites (if not supplied with unit) 

Position 

Refer to the Site Audit document for location. 
Check the site drawings for details regarding hazardous areas. If in any doubt about the 

location, refer to the site manager. 
Install the OPT in a sheltered position and if possible, facing away from prevailing wind and 
rain direction. 
If possible, install out of direct sunlight to avoid raising the temperature inside the OPT 
cabinet more than necessary. 
Situate the OPT so the PIN pad display will not be in direct sunlight at any time during the 

day as it makes it hard to read.  
Make sure that you position the OPT to ensure you can open the cabinet door. If mounted 

on a post, you must also allow clearance be able to remove and replace the access panel 
on the post. 

Содержание OPT SCR200

Страница 1: ...OPT SCR200 Installation Manual Version No 1 0 3 Model OPT Mark 2 SCR200 Date 7th December 2018...

Страница 2: ...ac C4000 processor s performance Compac Industries Limited has no control over each installation s unique operating environment Hence Compac Industries Limited makes no representations or warranties c...

Страница 3: ...t any time This publication describes the state of the product at the time of publication and may not reflect the product at all times in the past or in the future Manufactured By The Compac OPT SCR20...

Страница 4: ...ion Date 06 03 2018 Authorised By W Zheng File Name OPT SCR200 Installation Manual Revision History Version Date Author s Revision Notes 1 0 0 06 Mar 2018 S Laycock New Manual 1 0 1 20 Mar 2018 S Layc...

Страница 5: ...ts 2 Tools Checklist 3 Precautions 4 Mechanical Installation 5 Mounting the OPT on a Post 6 Electrical Installation 7 Cable Requirements 7 Electrical Testing 9 Tank Gauging Setup 11 System and Transac...

Страница 6: ...1 Footprints Footprints Base Footprint External Dimensions...

Страница 7: ...Secure Card Reader Camlock Optional IP Phone Speaker Payment Express SKP200 PIN pad Privacy Shield Optional IP Phone Mic and Button Vent Security PIN pad Optional 3G Router Net Switch MX Box UPS Board...

Страница 8: ...iver 7mm nut driver 8mm nut driver T30 Torx drive bit or driver T10 Torx drive bit or driver Metric spanner set Metric 3 8 or 1 4 drive socket set 1 4 screwdriver bit holder 1 4 A F spanner 6 adjustab...

Страница 9: ...nser The OPT should be placed at least 0 5 metres from any flammable liquid fuel dispensers and 1 5 metres from any LPG dispensers The OPT should be mounted so that the base of the cabinet is at least...

Страница 10: ...lowing equipment Mechanical and electrical tools Multimeter Fastenings to mount the OPT Security key drivers Security TORX or unique security key if Extra Security equipped A fully charged laptop comp...

Страница 11: ...OPTs do not have the bolt covers Fasten using the supplied galvanised bolts with the rounded head facing out and a flat washer under the nut To mount the OPT onto the post OPTs with the extra securit...

Страница 12: ...ed depending on the brand of pump on site Correct polarity must be observed NOTE For pump comms tank gauging and ADSL connections it is suggested that the wires are crimped to a ferrule to provide a g...

Страница 13: ...le at the bottom of the aerial for when the spring flexes A loop of 50mm before fixing the cable should be sufficient The aerial plugs into the wireless router Neatly cable tie the aerial cable to exi...

Страница 14: ...turned on two LEDs above the power switch should turn on LED labelled D5 indicates the 230V mains power is OK D6 indicates the battery is connected and OK If D6 does not light up when then unit is fi...

Страница 15: ...10 Electrical Testing UPS Board LEDs FMS Board LEDs Diagnostic LEDs...

Страница 16: ...hecks to confirm this The exact site test setup and procedure will vary from customer to customer but as a minimum we would suggest the following Check that the current price is correct Check each dis...

Страница 17: ...ounted appropriately Wireless internet OPTs Check that the pump comms have been connected Check that the tank gauging is connected and operating correctly where fitted Replace ATG cable to OPT where p...

Страница 18: ...orrect Tank Information Tests where fitted Yes No Check that tanks are set up in CompacOnline and that correct information from the equipment is being displayed on screen Check that the correct fuels...

Отзывы: