5. If the panel is being installed in a 19-inch rack or cabinet, remove the 23-inch mounting
brackets and install 19-inch brackets at the required recess (2, 4, or 5 inches) position, as
shown in
. Tighten screws to the torque specification shown in
6. Secure the panel shell to the rack or cabinet using the four 12-24 screws and star washers
(per local practice) provided, as shown in
Figure 37. Mounting the Panel Shell in the Rack
7. Connect a grounding wire to the panel shell as shown in
using the two screws
and star washers provided. (Two locations are available; see
two-hole grounding lug (shown here for reference) is recommended for the connection.
Figure 38. Grounding the Rapid Fiber Panel Chassis
Note:
Ground the unit to the local facility CBN (Common Bonding Network) or IBN
(Isolated Bonding Network) per local practice.
26201-A
12-24 SCREW
AND WASHER
(4 PLACES)
PROVIDE AT LEAST 3 INCHES (7.6 CM) OF
CLEARANCE AT THE REAR SIDE OF THE
PANEL TO ALLOW THE SPOOL TO ROTATE
FREELY AS THE CABLE IS UNWOUND
3 INCHES
26358-A
GROUND LUG & WIRE (NOT PROVIDED)
10-32
SCREWS
STAR
WASHERS
REAR
GROUNDING
LOCATION
NOTE: FRONT GROUNDING IS NOT
AVAILABLE WHEN THE MOUNTING
BRACKETS ARE INSTALLED IN THE