ZEFNET Pro User Manual
11
INSTALLATION - SERVICE CONNECTIONS
CAUTION: To reduce the risk of fire, connect only to a circuit
provided with the appropriate maximum branch circuit
overcurrent protection in accordance with the National Electrical
Code, ANSI/NFPA 70 (US) or the Canadian Electric Code C22.2
NO. 280-13 (Canada).
Table 1: Service Connections for ZEFNET Pro units
ZEFNET Pro Model
Load Balancing Circuit Breaker Rating
ZEFNET-Pro-40
No
2 x 40A
ZEFNET-Pro-40
Yes
1 x 40A
ZEFNET-Pro-60
No
2 x 60A
ZEFNET-Pro-60
Yes
1 x 60A
ZEFNET-Pro-80
No
2 x 80A
ZEFNET-Pro-80
Yes
1 x 80A
Load balancing refers to ZEFNET software settings that allow the ZEFNET
Pro to share a single circuit entering the unit, instead of the standard two
dedicated circuits the ZEFNET Pro typically requires.
CAUTION:
This is a single-phase device. Do not connect all
three phases of a 3-phase feed!
You may use any two phases
of a three phase wye-transformer feed. The centerpoint of the
three phases (usually used as Neutral) must be grounded
somewhere in the system. A Neutral connection is not required
by the ZEFNET Pro. Only Line 1, Line 2, and Ground are
required, as shown in
Figure 3.