C L I M AT E M A S T E R W AT E R - S O U R C E H E AT P U M P S
C o n s o l e s
R e v. : 5 N o v. , 2 0 0 9 B
6
C l i m a t e M a s t e r W a t e r- S o u r c e H e a t i n g a n d C o o l i n g S y s t e m s
General Information
Inspection
Upon receipt of the equipment, carefully check the
shipment against the bill of lading. Make sure all units
have been received. Inspect the packaging of each unit,
and inspect each unit for damage. Insure that the carrier
makes proper notation of any shortages or damage on all
copies of the freight bill and completes a common carrier
inspection report. Concealed damage not discovered
during unloading must be reported to the carrier within
15 days of receipt of shipment. If not
fi
led within 15 days,
the freight company can deny the claim without recourse.
Note: It is the responsibility of the purchaser to
fi
le all
necessary claims with the carrier. Notify your equipment
supplier of all damage within
fi
fteen (15) days of shipment.
Storage
Equipment should be stored in its original packaging in
a clean, dry area. Store units in an upright position at all
times. Stack units a maximum of 3 units high.
Unit Protection
Cover units on the job site with either the original
packaging or an equivalent protective covering. Cap
the open ends of pipes stored on the job site. In areas
where painting, plastering, and/or spraying has not been
completed, all due precautions must be taken to avoid
physical damage to the units and contamination by foreign
material. Physical damage and contamination may prevent
proper start-up and may result in costly equipment clean-
up.
Examine all pipes,
fi
ttings, and valves before installing
any of the system components. Remove any dirt or
debris found in or on these components.
Pre-Installation
Installation, Operation, and Maintenance instructions
are provided with each unit. Horizontal equipment is
designed for installation above false ceiling or in a ceiling
plenum. Other unit con
fi
gurations are typically installed
in a mechanical room. The installation site chosen
should include adequate service clearance around the
unit. Before unit start-up, read all manuals and become
familiar with the unit and its operation. Thoroughly check
the system before operation.
Prepare units for installation as follows:
1. Compare the electrical data on the unit nameplate
with ordering and shipping information to verify that
the correct unit has been shipped.
2. Keep the cabinet covered with the original packaging
until installation is complete and all plastering,
painting, etc. is
fi
nished.
3. Verify refrigerant tubing is free of kinks or dents and
that it does not touch other unit components.
4. Inspect all electrical connections. Connections must
be clean and tight at the terminals.
5. Remove any blower support packaging.
6. Loosen compressor bolts on units equipped with
compressor spring vibration isolation until the
compressor rides freely on the springs. Remove
shipping restraints.
7. REMOVE COMPRESSOR SUPPORT PLATE 1/4”
SHIPPING BOLTS (2 on each side) TO MAXIMIZE
VIBRATION AND SOUND ATTENUATION.
CAUTION!
DO NOT store or install units in corrosive
environments or in locations subject to temperature or
humidity extremes (e.g., attics, garages, rooftops, etc.).
Corrosive conditions and high temperature or humidity can
signi
fi
cantly reduce performance, reliability, and service life.
Always move and store units in an upright position. Tilting
units on their sides may cause equipment damage.
NOTICE!
Failure to remove shipping brackets from spring-
mounted compressors will cause excessive noise, and could
cause component failure due to added vibration.
CAUTION!
CAUTION!
CAUTION! CUT HAZARD
- Failure to follow this caution
may result in personal injury. Sheet metal parts may have
sharp edges or burrs. Use care and wear appropriate
protective clothing, safety glasses and gloves when
handling parts and servicing heat pumps.