Installation Guide_PV-ezRack_ezShade_AU_V1.0
1/10 Duerdin Street, Clayton VIC 3168 Australia
Tel: +61 3 9239 8088 Fax: +61 3 9239 8024
E-mail: [email protected] www.clenergy.com.au
20
page
of 25
Fig.23
Fig.24
Note:
Cut off the extra Rubber for Dry Bar by scissor.
Slide the T-bolt kit into groove of Dry Bar-Portrait, and turn the kit clockwise until it can’t move
anymore as shown in Fig 23.
Fasten M6 Nuts and T head bolts with Socket Spanner 10mm tightly as shown in Fig 23.
Note: Please note that grease must be applied and tool speed must be controlled while fastening the bolts.
Installation Instruction
5.2.4 Fix the Dry Bar-Portrait
Place the Dry Bar-Portrait between two adjacent rows of PV modules as shown in Fig 23.
Apply 4 sets T bolt kit between
Two PV Modules as shown
in Fig 24.
Recommended torque:
M6 bolts is 5-6 N.m
Repeat the above steps
until the whole array
installation is completed
as shown in Fig 25.