Installation Instruction
5.1.3 Fix the Main Support Beam
Slide 6 sets of M8 Cup head square neck bolts along the half slot of each Main Support Beam. Fasten each
Splice for Main Support Beam with two sets of M8 bolt assembly slightly by Socket Spanner 13mm. Take the
other Main Support Beam and fix it with Splices by the above steps. Do not fasten the M8 bolts tightly before the
end faces of Main Support Beams aligned as shown in Fig 4.
Fig. 4
5.1.4 Fix the assembled Main Beam into Rectangular Tube
Insert the assembled Main Beam into Rectangular Tube, align the holes and fasten with M16 Bolts
assembly by Socket Spanner 24mm as shown in Fig 5. Double-check all bolts are fastened tightly.
Note: Laying down the Main Beam and Rectangular Tube on ground will be easier to assemble.
Please note that grease must be applied and tool speed must be controlled while fastening the bolts.
Fig. 5
Recommended Torque:
M16: 135~150N·m