Installation Instruction
5.2.2 Fix the Dry Bar-Landscape
After PV Module installation, place the Dry Bar-Landscape & Dry Bar-Landscape (with Bushing) into
T-rail as shown in Fig16.
Fig. 16
Note: Cut off the extra Rubber for Dry Bar by scissor.
The Dry Bar-Landscape with Bushing should be placed on the first and last row as shown in Fig 16.
Click the Dry Bar-Landscape or Dry Bar-Landscape (with Bushing) into the U slot of T-rail.
Make sure the T head bolt slide into the groove of T-rail as shown in Fig 17.
Fig. 17