Installation Guide_PV-ezRack_ezShade_AU_V1.0
1/10 Duerdin Street, Clayton VIC 3168 Australia
Tel: +61 3 9239 8088 Fax: +61 3 9239 8024
E-mail: [email protected] www.clenergy.com.au
10
page
of 25
Installation Instruction
Fig. 1
5.1 Post and Main Beam Installation
5. Installation Instruction
Mark out the positions for bolts and embed
2 pcs of M20 bolt in each position as shown in
Fig 1.
Make sure all M20 bolts are aligned in both
horizontal and vertical direction as shown in
Fig 2. Make sure all M20 bolts are aligned in
both horizontal and vertical direction.
The distance between two bolts for Trapezoidal
U-anchor Plate 300 and 380 is 200mm and 280mm
respectively. All embedded bolts will
be revealed 60mm~80mm above the ground as
shown in Fig 1.
Note: The M20 bolts and matching nuts, washers
and spring washers are provided by installer.
5.1.1 Embed 2 pcs of M20 bolt
5.1.1 Fix the Rectangular Tubes into the Trapezoidal U-anchor Plate
Place the Rectangular Tube into the Trapezoidal U-anchor Plate 300,
align the holes and fix with M16 bolts assembly. Place the other two
Rectangular Tubes into the Trapezoidal U-anchor Plate 380 one by one,
align the holes and fix with M16 bolts assembly as shown in Fig 3.
Please refer to the engineering drawings for the size of the Rectangular
Tube. Recommended Torque: M16: 135~150 N
Fig. 3
Fig. 2