5.2.1 Fix the Rail splice into T Rail
In order to form a longer section, Splices may be used to join two T Rails. Insert Splice halfway into end of first
T Rail, apply Corrugated Shim on outside and fasten using self-drilling screws. Slide second T Rail over splice,
apply Corrugated Shim on outside and fasten using self-drilling screws as shown in Fig 9.
Note: Make sure the Corrugated Shim can match well with the corrugated face of T Rail.
5.2 Rail Installation
Fig. 9
5.2.2 Fix the T Rail onto Main Beam
Place the T Rail on the assembled Main Beam as shown in Fig 10. Apply Rail Clamp to fix the T Rail on the
assembled Main Beam and fasten Rail Clamps by Allen Key 6mm as shown in Fig 11.
Fig. 10