Maintenance
20
7.
Maintenance
The generator contains a list of components subject to wear and tear. In order
to guarantee an adequate programmed mainentance, for each one of these
components is set a working-time during testing phase.
During the operation, this time is decreased till its expiry and when it is over the
control board generates a maintenance request automatically.
7.1.
Deadline warnings
During production, when the forecasted autonomy of a components expires, a
message is diplayed, such as the example below:
WARNING
EXHAUSTING SILENCER
In order to acquire the warning please press function key
.
After that the
message disappears to proceed with normal operation.
At the next start-up, the generator asks if the maintenance operation has been
performed displaying the following message (referring to previous example):
SUBSTITUTION OF THE SILENCERS COMPLETED?
NO
Pressing up arrow key
” select “YES” or “NO” consequentely. After selecting
the reply, press the function key to acquire it.
If you reply “NO”, to next start-up, the message will be displayed again, while,
replying “YES”, the working time of the component will be reset (the one set up
at the beginning of count-down) for future maintenance.
Should the alarm of incorrect switch-off be present at start-up time, this proce-
dure isn’t activable: it will be anyway available to next start-up.
All manuals and user guides at all-guides.com