Raption 150 Series Installation Manual
6
A
Verification
Once completed the entire installation procedure, check the following points:
•
Check that all the MCB, RCD, Main Circuit Breaker and Disconnectors are powered
on.
•
Check that all safety labels are correctly placed.
•
Close the Charge Point’s doors. The Charge Point has a security switch (anti-
tamper protection) installed that will avoid any charging session if the doors are
opened.
•
Check that all beacons are illuminated in green.
•
Verify that each EV connector is in good condition.
•
Make sure the ventilation air flow is correct and there is not any obstruction at the air
inlets and outlets.
•
Check for abnormal noise while charging a vehicle.
Содержание Raption 150 Series
Страница 1: ...Installation Manual Raption 150 Series ...
Страница 2: ......
Страница 4: ......
Страница 7: ...03 ...
Страница 20: ...16 Raption 150 Series Installation Manual Power Unit front door Power input supply ...
Страница 21: ...17 Power Unit rear door Output wiring to Dispenser ...
Страница 27: ...23 1 2 3 4 ...
Страница 34: ...30 Raption 150 Series Installation Manual E Dispenser template dimensions 435 300 70 ...
Страница 35: ...31 400 165 280 310 ...
Страница 37: ...33 0 1920 ...
Страница 40: ...36 Raption 150 Series Installation Manual H Power Unit template dimensions 250 350 50 50 850 714 ...
Страница 42: ...38 Raption 150 Series Installation Manual Concrete basement dimensions for Power Unit J 0 2100 ...
Страница 51: ...47 CCS CCS CHA CHA 3 ...
Страница 53: ...49 PE DC 2 L N PE ETHERNET CABLE 2 1 3 DC 1 2 2 Wiring connection for the Dispenser Scheme ...
Страница 55: ...51 L1 N PE ETHERNET 1 2 ...
Страница 56: ...52 Raption 150 Series Installation Manual CCS CCS 3 ...
Страница 57: ...53 CHA PE CHA 3 ...
Страница 59: ...55 ...
Страница 65: ...61 ...
Страница 66: ...62 Raption 150 Series Installation Manual 8 ...