62
15 - START-UP CHECKLIST FOR 30XB(E/P)ZE LIQUID CHILLERS (USE FOR
JOB FILE)
Unit start-up
a. Oil heaters have been energized for at least 24 hours
b. Oil level is correct
c. All discharge and liquid valves are open
d. All suction valves are open, if equipped
e. All oil line valves and economizer discharge bubbler valves (if equipped) are open
f. Checks have been carried out for any possible leaks. Unit has been leak checked (including fittings)
g1 - on the whole unit
g2 - at all connections
Locate, repair, and report any refrigerant leaks .....................................................................................................................
..............................................................................................................................................................................................
..............................................................................................................................................................................................
g. Check voltage imbalance: AB .......................AC .......................BC ............................
Average voltage = ........................................ V
Maximum deviation = ................................... V
Voltage imbalance = ....................................%
h.
Voltage imbalance is less than 2%
WARNING: Operation of the chiller with an improper supply voltage or excessive phase imbalance constitutes abuse and will invalidate
the Carrier warranty. If the phase imbalance exceeds 2% for voltage, or 10% for current, contact your local electricity supply at once and
ensure that the chiller is not switched on until corrective measures have been taken.
Check cooler water loop
Water loop volume = ........................................litres
Calculated volume = ........................................litres
3.25 litres/nominal kW capacity for air conditioning
6.5 litres/nominal kW capacity for process cooling
Proper loop volume established
Proper loop corrosion inhibitor included ............litres of ...........
Proper loop freeze protection included (if required) .................litres of .........................
Piping includes electric heater tape, if exposed to the outside
Inlet piping to cooler includes a 20 mesh strainer with a mesh size of 1.2 mm
Check pressure drop across the cooler
Entering cooler = ..............................................kPa
Leaving cooler = ...............................................kPa
Leaving - entering = .........................................kPa
WARNING: Plot cooler pressure drop on performance data chart (in product data literature) to determine total litres per second (l/s)
and find unit’s minimum flow rate.
Total = ...............................................................l/s
Nominal kW = ...................................................l/s
Total l/s is greater than unit’s minimum flow rate
Total l/s meets job specified requirement of
...................................l/s
WARNING: Once power is supplied to the unit, check for any alarms. Refer to the SmartVu
TM
control manual for the alarm
menu.
Note all alarms:
......................................................................................................................................................................................
.............................................................................................................................................................................................................
Notes:
.....................................................................................................................................................................................................
.................................................................................................................................................................................................................