2.5
HIGH TEMP MESH
The High Temp Mesh is an open weave carbon mesh and must be obtained from
CARBOLINE
.
The application details of the High Temp Mesh are dependent upon the
design, size of steel, project requirements, etc. and can be found in the appendices of
this manual.
High Temp Mesh is utilized for Intertek Design No. CC/CA 180-03.
3.0
EQUIPMENT (Minimum)
3.1
APPROVED PLURAL COMPONENT EQUIPMENT FOR THERMO-LAG 3000 A AND
THERMO-LAG 3000 SA
The following approved plural component units (without holding tanks) are suitable for the
application of THERMO-LAG 3000 shall be purchased from:
AirTech Spray Systems, Inc.
CoverCat Spray Systems Ltd.
4303 Piedmont Dr.
35A Northfield Way, Newton Aycliffe
Houston, TX 77018
County Durham, DL5 6UF UK
Tel: 713-681-0013
Tel: 44-1325-314120
MODEL NO
:
MODEL NO
:
AT2.3/4000 (Bucket Pump)
352 F (Tank Mounted Pump)
452 F (Tank Mounted Pump)
Spray-Quip, Inc.
1754 Des Jardines
Covercat U.S.A.
Houston, TX 77023
40 Austin Boulevard
Tel: 713-923-2771
Commack, NY 11725
MODEL NO
631-462-2952:
397-884 SQ/GRACO H.D. Fixed Ratio
(Tank Mounted Pump)
We recommend the use of tank mounted pumps.
It is essential that all the equipment used by the Applicator is properly maintained. It is
necessary to regularly change items such as seals, gun tips, packing and hoses.
Every Applicator shall obtain a parts list and/or manual from the manufacturer for the proper
operation of the equipment and its maintenance.
Any company which has not utilized the specific pump prior to applying THERMO-LAG 3000
shall be trained in the proper operation of the pump by the pump manufacturer.
CARBOLINE takes no responsibility for the lack of proper instruction on the use of the
pump.
Poorly maintained equipment will not function properly and may cause the ratio of
components A and B, (set at 1:1), to vary. The permitted ratio tolerance of components A
and B is +/- 5% (by volume). The Applicator shall perform at least 2 ratio checks (by
volume) per shift collecting a minimum of 2.5 gallons (10 liters) of components A and B
during each check.
Ratio checks shall only be performed by pumping both components into separate pails
simultaneously.
Содержание Thermo-Lag 3000
Страница 21: ...Page 14 of 35 APPENDIX A THERMO LAG 3000 ACCEPTABLE PRIMER LIST...
Страница 23: ...Page 16 of 35 APPENDIX B THERMO LAG 3000 ACCEPTABLE TOPCOAT LIST...
Страница 25: ...Page 18 of 35 APPENDIX C THERMO LAG 3000 ASTM E119 DESIGNS...
Страница 38: ...Page 31 of 35 APPENDIX D THERMO LAG 3000 TYPICAL APPLICATION LOGS...
Страница 40: ...Page 33 of 35...
Страница 41: ...Page 34 of 35...
Страница 42: ...Page 35 of 35...