Appendix G. CS110 2 Meter CM10 Tripod Site
FIGURE G-2. CS110 on CM10 Tripod Mast
Mount the fibreglass enclosure to the top of the leg facing the equator with the top
bracket approximately 5 cm (2 inches) below the top of the leg. Be careful
opening the lid because in this almost horizontal position it is possible to pull the
hinge rivets out of the enclosure.
If there is a solar panel, install the solar panel on the leg facing the equator below
the enclosure. Tilt the solar panel at an angle less than horizontal that is equal to
the latitude plus 10 degrees (see solar panel manual).
Ground the CS110 Electric Field Meter (Figure G-2), the tripod, and the battery
(through the enclosure ground) with three separate ground wires as shown in
Figure G-3. Power and communication cables should be run down the equator
side of the mast and under the enclosure as shown. Wire-tie all cables into place
so they don’t move with the wind.
G-3
Содержание CS110
Страница 2: ......
Страница 4: ......
Страница 6: ......
Страница 10: ...iv This is a blank page ...
Страница 37: ...Instruction Manual 27 ...
Страница 48: ......
Страница 52: ...Appendix B CS110 Accessories This is a blank page B 2 ...
Страница 56: ...Appendix C CS110 Connector Pin outs C 4 This is a blank page ...
Страница 72: ...Appendix F Example CRBasic Programs This is a blank page F 4 ...
Страница 78: ...Appendix G CS110 2 Metre CM10 Tripod Site This is a blank page G 6 ...
Страница 85: ......