6. Commissioning
Before commissioning you have to check if the connection data of the device match the
data of the plant (see nameplate).
If so, you can start to put the device into operation by switching on the power supply and
the measurement inputs.
AM1000
Measurement input
Input voltage
Input current
System frequency
1 Serial number
2 Test and conformity marks
3 Assignment voltage inputs
4 Assignment current inputs
5 Assignment power supply
6 Load capacity relay outputs
AM2000 / AM3000
Measurement input
Input voltage
Input current
System frequency
1 Works no.
2 Test and conformity marks
3 Assignment voltage inputs
4 Assignment current inputs
5 Assignment power supply
6 Load capacity relay outputs