Placing the Boiler in Operation
7
24
We reserve the right to make any changes due to technical modifications!
Boiler Installation and Maintenance Manual SB735 • Issue 10/2003
Buderus Heiztechnik GmbH • http://www.heiztechnik.buderus.de
7
Placing the Boiler in Operation
A
DANGER!
due to combustion products.
Prior to placing the boiler in operation, put 3 or
4 gallons of water in the clean-out opening or
combustion chamber to fill the drain in the
condensate drain line (Fig. 27,
Item.
3).
A
BOILER DAMAGE!
due to corrosion and debris build-up.
Flush the entire heating system prior to firing the
boiler. To avoid corrosion and debris build-up
on the water side of the boiler. It is required to
test the fill and make-up water per Instructions
for Water Preparation for Boiler.
D
NOTICE!
Observe the installation instructions for the
neutralization system!
Follow the instructions supplied with boiler,
burner, controls and low water cut-off
components during the start-up of the system.
Make the end user familiar with the function and
operation of the entire system and sign over the
technical documentation.
It is recommended to instruct the end user
regarding maintenance requirements and
procedures. An annual service contract is
recommended.