Commissioning report
▶ Initial and date the commissioning steps carried out.
Commissioning steps
Page
Readings taken
Remarks
1.
Fill heating system and check for leaks
–
Heating system filling pressure
__________________ psi
2.
Details in "Water quality requirements for Logano plus GB312"
manual taken into account
–
Concentration of any additives
Add.:______________ Conc.:__________%
3.
Record gas characteristics: calorific value
42
__________________ BTU/ft³
4.
Check gas pipe for leaks
42
Bleeding the gas supply pipe
51
5.
Bring the system up to operating pressure
41
6.
Check air intake and outlet openings and flue connector
43
7.
Checking the air inlet diaphragm
43
8.
Checking appliance equipment
42
9.
Starting up the control panel and the burner
44
10.
Adjust burner setting if necessary
45
11.
Record readings taken
48
Maximum load
Minimum load
Pressure differential
____________in W.C. ____________in W.C.
Flue gas temperature
________________ °F ________________ °F
Air temperature
________________ °F ________________ °F
Carbon dioxide level (CO
2
)or oxygen content (O
2
)
________________ %
________________ %
Carbon monoxide content (CO), free of air
_____ ppm
_____ ppm
12.
Measuing the gas supply pressure
53
____________in W.C.
13.
Checking for leaks during operation
53
14.
Function testing
52
Testing ionization current
____________ μA
15.
Installing jacket panels
54
16.
Inform operator and hand over technical documentation
54
17.
Correct commissioning confirmed by installer
Signature:___________________________________________________
18.
Signature of operator
Signature:___________________________________________________
Table 18 Commissioning report
Содержание Logano plus GB312
Страница 93: ...Logano plus GB312 6 720 806 273 2013 01 93 Notes ...
Страница 94: ...Logano plus GB312 6 720 806 273 2013 01 94 Notes ...
Страница 95: ...Logano plus GB312 6 720 806 273 2013 01 95 Notes ...
Страница 96: ......