7
We reserve the right to make any changes due to technical modifications.
Installation and maintenance instructions Logano GE315 • Issue 02/2006
2
Installation
2
Installation
2.1
Standard delivery
The Logano GE315 boiler can be supplied as ready
assembled block or in individual boiler segments.
2.1.1
Pre-assembled delivery
1
Pallet: Boiler block
with burner door and feed pipe
1
Cartons: Casing
(depending on boiler size)
1
Foil packaging: Thermal insulation
2.1.2
Supplied in sections
1
Pallet: Front and rear segment
3 central segments and burner door
1
Pallet: Central segments – depending on boiler
size
1
Carton: Mounting components and flue gas
collector
1
Bundle: Tie bars and return header
1
Cartons: Casing
(depending on boiler size)
1
Foil packaging: Thermal insulation