7
Boiler block assembly
Logano G615 - Subject to technical modifications
28
7.9
Installing draft diverter, baffles, and
burner door
The next step in the assembly process is to install the
burner door and draft diverter. The pre-assembled boiler
comes with these components already installed.
7.9.1
Positioning the draft diverter
The GP sealant rope (fiberglass cord with silicon casing)
which forms a seal is inserted in the draft diverter at the
factory.
B
Glue GP sealant rope (approx. 59 1/16 inches
(1500 mm) long) into the groove on the rear section
using adhesive.
B
Insert the sealant rope in such a way that its joint is at
the top of the groove.
B
Place the draft diverter onto the four threaded studs on
the rear section and secure using washers and nuts.
Fig. 28 Positioning the draft diverter
1
Sealant rope joint at the top of the groove
2
Sealant rope
3
Draft diverter
4
Threaded studs
5
Rear section
6
Threaded studs
7.9.2
Screwing cleanout cover onto rear section
Fig. 29 shows the fully equipped rear section with the
cleanout covers on the draft diverter and the cleanout
covers on the rear section.
B
GP10Glue GP sealant rope (approx. 31 1/2 inches
(800 mm) long) into the groove on the rear section with
Silastic adhesive (sealant rope joint at top).
B
Secure the cleanout covers on the rear section with
washers and nuts.
Fig. 29 Securing the cleanout covers
1
Cleanout cover on the draft diverter
2
Cleanout cover on the draft diverter
3
Cleanout cover on the rear section
4
Cleanout cover on the rear section
2
6 720 642 625-26.1o
3
1
4