7
STEP 1
(Selecting Site)
Before installing your new lift, check the following.
1.
LIFT LOCATION
: Always use architects plans when
available. Check layout dimension against floor plan
requirements making sure that adequate space if avail-
able.
2.
OVERHEAD OBSTRUCTIONS
: The area where
the lift will be located should be free of overhead
obstructions such as heaters, building supports,
electrical lines etc.
3.
DEFECTIVE FLOOR
: Visually inspect the site where
the lift is to be installed and check for cracked or
defective concrete.
4.
OPERATING TEMPERATURE.
Operate lift only
between temperatures of 41° -104° F.
5. Lift is designed for
INDOOR INSTALLATION ONLY.
Outdoor use permitted only if covered and dry. Always
follow warnings illustrated on equipment labels.
STEP 2
(Floor Requirements)
This lift must be installed on a solid level concrete
floor with no more than 3-degrees of slope. Failure
to do so could cause personal injury or death.
A level floor is suggested for proper use and
installation and level lifting. If a floor is of questionable
slope, consider a survey of the site and/or the possibility
of pouring a new level concrete slab.
t
DO NOT
install or use this lift on any asphalt surface
or any surface other than concrete.
t
DO NOT
install or use this lift on expansion seams
or on cracked or defective concrete.
t
DO NOT
install or use this lift on a second / elevated
floor without first consulting building architect.
LIFT MODEL CONCRETE REQUIREMENTS
XPR-9S
4” Min. Thickness / 3,000 PSI
XPR-9S-LP 4” Min. Thickness / 3,000 PSI
XPR-9TS
4” Min. Thickness / 3,000 PSI
All models MUST be installed on 3000 PSI concrete
only conforming to the minimum requirements
shown above. New concrete must be adequately
cured by at least 28 days minimum.
IMPORTANT NOTICE
These instructions must be followed to ensure proper installation and operation of your lift. Failure
to comply with these instructions can result in serious bodily harm and void product warranty.
Manufacturer will assume no liability for loss or damage of any kind, expressed or implied resulting
from improper installation or use of this product.
PLEASE READ ENTIRE MANUAL PRIOR TO INSTALLATION
t
Rotary Hammer Drill or Similar
t
3/4” Masonry Bit
t
Hammer
t
4 Foot Level
t
Open-End Wrench Set: SAE/Metric
t
Socket And Ratchet Set: SAE/Metric
t
Hex-Key / Allen Wrench Set
t
Large Crescent Wrench
t
Large Pipe Wrench
t
Crow Bar
t
Chalk Line
t
Medium Flat Screwdriver
t
Tape Measure: 25 Foot Minimum
t
Needle Nose Pliers
TOOLS REQUIRED
IMPORTANT NOTE:
BendPak lifts are supplied with installation instructions and concrete fasteners meeting the criteria as
prescribed by the American National Standard "Automotive Lifts - Safety Requirements for Construction, Testing,
and Validation" ANSI/ALI ALCTV-2011. Lift buyers are responsible for any special regional structural
and/or seismic anchoring requirements specified by any other agencies and/or codes such as the
Uniform Building Code (UBC) and/or International Building Code (IBC).
CONCRETE
SPECIFICATIONS